AIA - the procedure for obtaining, the main problems and methods of solution. Metering devices for used energy resources Conclusion on the compliance of the constructed capital construction facility

The developer does not agree with the refusal to issue a commissioning permit

The authorized body wants to hold the organization (IE) responsible for the operation of the facility capital construction without permission to operate

An organization (IP) disputes holding liable for the operation of a capital construction facility without a commissioning permit

The plaintiff wants to recognize the ownership of the object of construction in progress

The applicant does not agree with the refusal to register the property for cadastral registration

See all situations related to art. 55 GK RF

1. Permission to commission an object is a document that certifies the completion of construction, reconstruction of a capital construction object in full in accordance with the construction permit, design documentation, as well as the compliance of the constructed, reconstructed capital construction object with the requirements for construction, reconstruction of a capital object construction, established on the date of issue of the urban planning plan of the land plot submitted for obtaining a construction permit, the permitted use of the land plot or, in the case of construction, reconstruction of a linear facility, the territory planning project and the land surveying project (except for cases in which construction, reconstruction of a linear facility is not preparation of planning documentation is required), a territory planning project in case of issuing a permit for the commissioning of a linear facility, the placement of which does not require the formation of a land plot, as well as restrictions established in accordance with land and other legislation Russian Federation.

ConsultantPlus: note.

The possibility of transmitting and receiving in an automated mode information and documents provided for in Part 2 of Art. 55, must be provided no later than one year from 06/27/2019 (FZ of 06/27/2019 N 151-FZ).

2. To put the object into operation, the developer applies to the federal executive authority, the executive authority of the subject of the Russian Federation, the local government, the State Atomic Energy Corporation "Rosatom" or the State Corporation for Space Activities "Roskosmos", which issued the construction permit, directly or through a multifunctional center with an application for a permit to put the facility into operation. Developers whose names contain the words "specialized developer" can also apply with the specified application using a single information system housing construction, except for cases where, in accordance with a regulatory legal act of a constituent entity of the Russian Federation, the issuance of a permit for putting an object into operation is carried out through other information systems that must be integrated with a unified information system for housing construction.

(see text in previous edition)

2.1. The federal executive body, the executive body of the constituent entity of the Russian Federation, the local self-government body, the State Atomic Energy Corporation "Rosatom" or the State Corporation for Space Activities "Roskosmos", authorized to issue permits for putting the object into operation, issue these permits in relation to the stages construction, reconstruction of capital construction facilities in the cases provided for by part 12 of article 51 and part 3.3 of article 52 of this Code.

ConsultantPlus: note.

Documents provided for in paragraph 13 of Part 3 of Art. 55 (in the previous edition), submitted before 08/04/2018 together with an application for issuing a permit to put the facility into operation, are an annex to the permit, and the permit itself is a decision to establish a buffer zone.

3. To make a decision on issuing a permit to put an object into operation, the following documents are required:

1) documents of title to a land plot, including an agreement on the establishment of an easement, a decision on the establishment of a public easement;

(see text in previous edition)

2) urban planning plan of the land plot submitted for obtaining a building permit, or in the case of construction, reconstruction of a linear facility, a territory planning project and a land surveying project (except for cases in which the construction, reconstruction of a linear facility does not require the preparation of territory planning documentation) , a territory planning project in the event that a permit is issued for the commissioning of a linear facility, the placement of which does not require the formation of a land plot;

(see text in previous edition)

3) building permit;

4) an act of acceptance of the capital construction object (in the case of construction, reconstruction on the basis of a contract building contract);

(see text in previous edition)

(see text in previous edition)

6) an act confirming the compliance of the parameters of the constructed, reconstructed capital construction object project documentation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility with metering devices for the energy resources used, and signed by the person carrying out the construction (the person carrying out the construction and the developer or technical customer in the case of construction, reconstruction on the basis of a construction contract, as well as the person exercising construction control, in the case of construction control on the basis of an agreement);

(see text in previous edition)

7) documents confirming the compliance of the constructed, reconstructed capital construction facility with the technical specifications and signed by representatives of organizations operating utility networks (if any);

(see text in previous edition)

8) a diagram showing the location of the constructed, reconstructed capital construction facility, the location of engineering and technical support networks within the boundaries of the land plot and the planning organization of the land plot and signed by the person carrying out the construction (the person carrying out the construction and the developer or technical customer in the case of construction, reconstruction on the basis of a construction contract), with the exception of cases of construction, reconstruction of a linear facility;

(see text in previous edition)

9) the conclusion of the state construction supervision body (in the event that state construction supervision is provided for in accordance with Part 1 of Article 54 of this Code) on the compliance of the constructed, reconstructed capital construction facility with the requirements of project documentation (including project documentation, which takes into account the changes made to in accordance with Parts 3.8 and 3.9 of Article 49 of this Code), including the requirements for energy efficiency and the requirements for equipping a capital construction facility with metering devices for used energy resources, the conclusion of the federal executive body authorized to exercise federal state environmental supervision (hereinafter referred to as the federal state environmental supervision body ) issued in the cases provided for by paragraph 7 of Article 54 of this Code;

(see text in previous edition)

10) a document confirming the conclusion of an agreement on compulsory insurance of civil liability of the owner of a hazardous facility for causing harm as a result of an accident at a hazardous facility in accordance with the legislation of the Russian Federation on compulsory insurance civil liability of the owner of a hazardous facility for causing harm as a result of an accident at a hazardous facility;

11) an act of acceptance of the work performed to preserve the object cultural heritage, approved by the relevant body for the protection of cultural heritage objects, determined by the Federal Law of June 25, 2002 N 73-FZ "On objects of cultural heritage (monuments of history and culture) of the peoples of the Russian Federation", when restoring, conserving, repairing this object and adapting it for modern use;

12) the technical plan of the capital construction facility, prepared in accordance with the Federal Law of July 13, 2015 N 218-FZ "On State Registration of Real Estate";

(see text in previous edition)

(see text in previous edition)

(see text in previous edition)

3.1. The document and opinion referred to in paragraphs 6 and 9 of paragraph 3 of this article must contain information about normative values indicators included in the energy efficiency requirements of the capital construction object, and on the actual values ​​of such indicators determined in relation to the constructed, reconstructed capital construction object as a result of studies, measurements, examinations, tests, as well as other information, on the basis of which compliance with such object to the requirements of energy efficiency and the requirements of its equipment with metering devices for the energy resources used. During construction, reconstruction apartment building the conclusion of the state building supervision body must also contain information on the energy efficiency class of the apartment building, determined in accordance with the legislation on energy saving and energy efficiency improvement.

(see text in previous edition)

3.2. The documents (their copies or information contained in them) specified in clauses 1, , and 9 of part 3 of this article are requested by the bodies specified in part 2 of this article, in state bodies, local governments and subordinate government bodies or local self-government organizations that have the said documents at their disposal, if the developer has not submitted the said documents on his own.

3.3. The documents specified in paragraphs 1, , , and 8 of part 3 of this article are sent by the applicant independently, if the indicated documents (their copies or information contained in them) are not at the disposal of state authorities, local governments or subordinate to state bodies or bodies local government organizations. If the documents specified in this part are at the disposal of state authorities, local governments or organizations subordinate to state bodies or local governments, such documents are requested by the body specified in part 2 of this article, in the bodies and organizations at the disposal of which the said documents, if the developer has not submitted these documents on his own.

(see text in previous edition)

3.4. At interdepartmental requests of the bodies specified in part 2 of this article, the documents (their copies or information contained in them) provided for in part 3 of this article are provided by state bodies, local governments and organizations subordinate to state bodies or local governments, at the disposal of which these documents are located no later than three working days from the date of receipt of the relevant interdepartmental request.

3.5. If an application is submitted for issuing a permit to put an object into operation in relation to the construction stage, reconstruction of a capital construction object, the documents specified in paragraphs 4, - 12 of part 3 of this article are drawn up in the part related to the corresponding stage of construction, reconstruction of the object capital construction. In this case, the application for issuing a permit to put an object into operation in relation to the construction stage, reconstruction of a capital construction object shall indicate information on previously issued permits to put the object into operation in relation to the construction stage, reconstruction of a capital construction object (if any).

4. The Government of the Russian Federation may establish, in addition to those provided for by part 3 of this article, other documents necessary for obtaining a permit to put an object into operation in order to obtain in full the information necessary for putting a capital construction object on state register.

4.1. In order to obtain a permit to put an object into operation, it is allowed to require only the documents specified in parts 3 and this article. The documents provided for by parts 3 and this article may be sent to electronic form. Permission to put the object into operation is issued in the form electronic document signed with an electronic signature, if this is indicated in the application for issuing a permit to put the facility into operation. The Government of the Russian Federation or the highest executive body of state power of a constituent entity of the Russian Federation (in relation to cases of issuing a permit for putting an object into operation by executive authorities of constituent entities of the Russian Federation, local authorities) may establish cases in which the direction of the documents specified in parts 3 and this article and the issuance of commissioning permits are carried out exclusively in electronic form. The procedure for sending the documents specified in parts 3 and this article to the federal executive authorities authorized to issue permits for putting the facility into operation, the executive authorities of the constituent entity of the Russian Federation, local governments, the State Atomic Energy Corporation "Rosatom" or the State Corporation for space activities "Roskosmos" in electronic form is established by the Government of the Russian Federation.

(see text in previous edition)

ConsultantPlus: note.

The term for consideration of an application for issuing a permit to put an object into operation, provided for in Part 5 of Art. 55 (as amended on December 27, 2019 N 472-FZ), does not apply if it was submitted before December 28, 2019.

5. The authority, the State Corporation for Atomic Energy "Rosatom" or the State Corporation for Space Activities "Roscosmos" that issued the construction permit, within five working days from the date of receipt of the application for issuance of a permit to put the facility into operation, must ensure the verification of the existence and correctness of execution of the documents specified in paragraph 3 of this article, inspection of the capital construction facility and issue the applicant a permit to put the facility into operation or refuse to issue such a permit, indicating the reasons for the refusal. During the inspection of the constructed, reconstructed capital construction object, the compliance of such an object with the requirements specified in the building permit, the requirements for construction, reconstruction of the capital construction object established on the date of issue of the urban planning plan of the land plot submitted for obtaining a construction permit is checked, or in the case of construction , reconstruction of a linear facility with the requirements of a territory planning project and a land surveying project (except for cases in which the preparation of documentation for planning the territory is not required for the construction, reconstruction of a linear facility), the requirements established by the territory planning project, in case of issuing a permit for commissioning a linear object, for the placement of which the formation of a land plot is not required, as well as the permitted use of the land plot, the restrictions established in accordance with the land and other legislation of the Russian Federation, the requirements of project documentation, including energy efficiency requirements and the requirements for equipping a capital construction object with metering devices used energy resources. If during the construction, reconstruction of a capital construction object, state construction supervision is carried out in accordance with part 1 of Article 54 of this Code, inspection of such an object by the body that issued the construction permit is not carried out.

(see text in previous edition)

6. The grounds for refusal to issue a permit to put the facility into operation are:

(see text in previous edition)

(see text in previous edition)

2) non-compliance of the capital construction object with the requirements for the construction, reconstruction of the capital construction object, established on the date of issue of the urban planning plan of the land plot submitted for obtaining a building permit, or in the case of construction, reconstruction, overhaul linear facility to the requirements of the territory planning project and the land surveying project (except for cases in which the construction, reconstruction of the linear facility does not require the preparation of territory planning documentation), the requirements established by the territory planning project, in case of issuing a permit for commissioning a linear facility, for the placement of which the formation of a land plot is not required;

(see text in previous edition)

3) non-compliance of the capital construction object with the requirements established in the building permit;

4) non-compliance of the parameters of the constructed, reconstructed capital construction facility with the design documentation;

(see text in previous edition)

5) non-compliance of the capital construction object with the permitted use of the land plot and (or) the restrictions established in accordance with the land and other legislation of the Russian Federation as of the date of issuance of a permit to put the object into operation, except in cases where these restrictions are provided for by the decision to establish or change the zone with special conditions for the use of the territory, adopted in the cases provided for by paragraph 9 of part 7 of Article 51 of this Code, and the capital construction object under construction, reconstructed, in connection with the placement of which a zone with special conditions for the use of the territory has been established or changed, has not been put into operation.

(see text in previous edition)

6.1. Non-receipt (late receipt) of the documents requested in accordance with parts 3.2 and 3.3 of this article cannot be grounds for refusing to issue a permit to put the facility into operation.

(see text in previous edition)

8. Refusal to issue a permit to put an object into operation may be challenged in court.

(see text in previous edition)

9. A permit to put an object into operation (with the exception of a linear object) is issued to the developer if the federal executive authority, the executive authority of the constituent entity of the Russian Federation, the local government, the State Atomic Energy Corporation "Rosatom" or the State Space Corporation activities of Roskosmos, which issued a construction permit, a copy of the diagram showing the location of the constructed, reconstructed capital construction facility, the location of engineering and technical support networks within the boundaries of the land plot and the planning organization of the land plot was transferred free of charge to place such a copy in the state information system for providing urban planning activities.

(see text in previous edition)

9.1. The federal executive body, the executive body of the constituent entity of the Russian Federation, the local self-government body, the State Corporation for Atomic Energy "Rosatom" or the State Corporation for Space Activities "Roskosmos", which issued the permit to put the object into operation, within five working days from the date of issue such permission is provided (including using unified system interdepartmental electronic interaction and regional systems of interdepartmental electronic interaction connected to it) transfer to those authorized for placement in state information systems ensuring urban planning activities, state authorities of the constituent entities of the Russian Federation, local governments of municipal districts, urban districts information, documents, materials specified in paragraphs 3, - 9.2, and 12 of part 5 of Article 56 of this Code.

10. Permission to put the object into operation is the basis for state registration of the constructed capital construction object, making changes to the documents state accounting reconstructed capital construction facility.

10.1. A mandatory annex to the permission to put the object into operation is the technical plan of the capital construction object submitted by the applicant, prepared in accordance with the Federal Law of July 13, 2015 N 218-FZ "On State Registration of Real Estate".

(see text in previous edition)

(see text in previous edition)

11. The permit to put the object into operation must contain information about the capital construction object in the amount necessary for the implementation of its state cadastral registration. The composition of such information must comply with the requirements established in accordance with the Federal Law of July 13, 2015 N 218-FZ "On State Registration of Real Estate" for the composition of information in the graphic and text parts of the technical plan.

(see text in previous edition)

11.1. After the completion of the construction of the capital construction object, the person carrying out the construction is obliged to transfer the results to the developer of such an object engineering surveys, project documentation, certificates of examination of works, structures, sections of networks of engineering and technical support of a capital construction object, other documentation necessary for the operation of such an object.

11.2. When carrying out work to preserve a cultural heritage object, a permit for commissioning such an object is issued taking into account the specifics established by the legislation of the Russian Federation on the protection of cultural heritage objects.

12. The form of permission to put the facility into operation is established by the authorized Government of the Russian Federation federal body executive power.

(see text in previous edition)

13. Within three working days from the date of issuance of a permit to put the object into operation, the body that issued such a permit sends a copy of such a permit to the federal executive body authorized to exercise state construction supervision, if a permit has been issued to put the facility into operation. capital construction, specified in paragraph 5.1 of Article 6 of this Code, or to the executive authority of the constituent entity of the Russian Federation authorized to exercise state construction supervision, if a permit has been issued for the commissioning of other capital construction facilities.

(see text in previous edition)

14. In the cases provided for by clause 9 of part 7 of article 51 of this Code, within three working days from the date of issuance of a permit for putting the facility into operation, the federal executive body, the executive body of the constituent entity of the Russian Federation, the local government, the State Atomic Energy Corporation Rosatom or the State Corporation for Space Activities Roscosmos, which issued such a permit, send (including using a unified system of interdepartmental electronic interaction and regional systems of interdepartmental electronic interaction connected to it) a copy of such permission to state authorities or local governments who made a decision to establish or change a zone with special conditions for the use of the territory in connection with the location of the facility, in respect of which a permit was issued to put the facility into operation.

ConsultantPlus: note.

Obtaining a permit to put the object into operation is not required also in the cases specified in Art. 16 FZ of 03.08.2018 N 340-FZ.

15. A permit to put an object into operation is not required if, in accordance with paragraph 17 of Article 51 of this Code, the issuance of a construction permit is not required for the construction or reconstruction of the object.

16. In case of construction or reconstruction of an individual housing construction object or a garden house, the developer, no later than one month from the date of completion of construction or reconstruction of an individual housing construction object or a garden house, shall apply for hard copy through a personal appeal to the federal executive body authorized to issue construction permits, the executive body of a constituent entity of the Russian Federation or a local government body, including through a multifunctional center, or sends it to these bodies by mail with acknowledgment of receipt or a single portal of state and municipal services notification of the completion of construction or reconstruction of an individual housing construction or garden house (hereinafter referred to as the notification of the completion of construction). The notice of completion of construction must contain the information provided for in paragraphs 1 - and 8 of part 1 of Article 51.1 of this Code, as well as information on the parameters of the constructed or reconstructed individual housing construction or garden house, on payment of the state fee for state registration of rights, on the method sending the developer a notice provided for in clause 5 of part 19 of this article. Attached to the notice of completion of construction:

2) the technical plan of the object of individual housing construction or a garden house;

3) an agreement concluded between the right holders of the land plot on the determination of their shares in the right of common fractional ownership for the constructed or reconstructed object of individual housing construction or garden house in the event that the land plot on which an individual housing construction object or a garden house is built or reconstructed belongs to two or more citizens on the right of common shared ownership or on the right of lease with a plurality of persons on the side of the tenant.

17. If the notice of completion of construction lacks the information provided for in paragraph one of part 16 of this article, or the documents attached to it and provided for in paragraphs 1-3 of part 16 of this article, as well as if the notice of completion of construction was received after expiration of ten years from the date of receipt of the notification of the planned construction, in accordance with which the construction or reconstruction of the individual housing construction object or garden house was carried out, or the notification of the planned construction of such an individual housing construction object or garden house was not previously sent (including it was returned to the developer in accordance with Part 6 of Article 51.1 of this Code), the federal executive body, the executive body of the constituent entity of the Russian Federation or the local self-government body authorized to issue construction permits, within three working days from the date of receipt of the notice of completion of construction, returns the notice of completion of construction to the developer and the documents attached to it without consideration, indicating the reasons for the return. In this case, the notice of completion of construction is considered not sent.

18. The form of notification of the completion of construction is approved by the federal executive body responsible for the development and implementation of public policy and legal regulation in the field of construction, architecture, urban planning.

19. The federal executive body, the executive body of a constituent entity of the Russian Federation or the local self-government body authorized to issue construction permits, within seven working days from the date of receipt of the notice of completion of construction:

1) checks the compliance of the parameters of the constructed or reconstructed individual housing construction object or garden house specified in the notice of completion of construction with the maximum parameters of permitted construction, reconstruction of capital construction objects, established by the rules of land use and development, territory planning documentation, valid on the date of receipt of the notice of planned construction , and mandatory requirements for the parameters of capital construction objects established by this Code, others federal laws(including in the event that the specified limit parameters or mandatory requirements for the parameters of capital construction objects are changed after the day the notification of the planned construction is received by the relevant authority and the notification of completion of construction confirms the compliance of the parameters of the constructed or reconstructed individual housing construction object or garden house with the limit parameters and mandatory requirements for the parameters of capital construction facilities in force on the date of receipt of the notification of the planned construction). If the notice of completion of construction confirms the compliance of the parameters of the constructed or reconstructed individual housing construction or garden house with the limiting parameters and mandatory requirements for the parameters of capital construction objects in force on the date of receipt of the notice of completion of construction, the conformity of the parameters of the constructed or reconstructed object of individual housing construction or a garden house to the specified limiting parameters and mandatory requirements for the parameters of capital construction objects in force on the date of receipt of a notice of completion of construction;

2) by examining the object of individual housing construction or garden house, checks the conformity of the external appearance of the object of individual housing construction or garden house with the description of the appearance of such an object or house, which is an annex to the notice of the planned construction 8 of Article 51.1 of this Code, no notification was sent about the non-compliance of the parameters of the individual housing construction object or garden house specified in the notice of planned construction with the established parameters and (or) the inadmissibility of placing the individual housing construction object or garden house on land plot on the grounds specified in clause 4 of part 10 of Article 51.1 of this Code), or a typical architectural solution, specified in the notice of planned construction, in the case of construction or reconstruction of an individual housing construction object or a garden house within the boundaries of a historical settlement of federal or regional significance;

3) checks whether the type of permitted use of an individual housing construction object or a garden house corresponds to the type of permitted use specified in the notice of planned construction;

4) checks the admissibility of placing an object of individual housing construction or a garden house in accordance with the restrictions established in accordance with the land and other legislation of the Russian Federation on the date of receipt of a notice of completion of construction, except in cases where these restrictions are provided for by a decision to establish or change a zone with special conditions for the use of the territory adopted in relation to the planned for construction, reconstruction of the capital construction object and such a capital construction object has not been put into operation;

5) sends the developer, in the manner specified in the notice of completion of construction, a notice on the compliance of the constructed or reconstructed individual housing construction or garden house with the requirements of the legislation on urban planning or on the non-compliance of the constructed or reconstructed individual housing construction or garden house with the requirements of the legislation on urban planning with indicating all the grounds for sending such a notice. Forms of notification of the compliance of the constructed or reconstructed individual housing construction object or garden house with the requirements of the legislation on urban planning activities, notification of non-compliance of the constructed or reconstructed individual housing construction object or garden house with the requirements of the legislation on urban planning activities are approved by the federal executive body responsible for the development and implementation of state policy and legal regulation in the field of construction, architecture, urban planning.

20. Notification of non-compliance of the constructed or reconstructed object of individual housing construction or a garden house with the requirements of the legislation on urban planning is sent only in the following cases:

1) the parameters of the constructed or reconstructed object of individual housing construction or garden house do not comply with the limiting parameters of permitted construction, reconstruction of capital construction objects specified in paragraph 1 of part 19 of this article, established by the rules for land use and development, territory planning documentation, or mandatory requirements for the parameters of objects capital construction, established by this Code, other federal laws;

2) the external appearance of an object of individual housing construction or a garden house does not correspond to the description of the external appearance of such an object or house, which is an appendix to the notice of planned construction, or to the standard architectural solution specified in the notice of planned construction, or a notice of discrepancy was sent to the developer about the discrepancy specified in notification of the planned construction of the parameters of an individual housing construction object or a garden house to the established parameters and (or) the inadmissibility of placing an individual housing construction object or a garden house on a land plot on the basis specified in paragraph 4 of part 10 of Article 51.1 of this Code, in the case of construction or reconstruction of the object individual housing construction or a garden house within the boundaries of a historical settlement of federal or regional significance;

3) the type of permitted use of the constructed or reconstructed capital construction object does not correspond to the type of permitted use of the individual housing construction object or garden house specified in the notice of planned construction;

4) placement of an object of individual housing construction or a garden house is not allowed in accordance with the restrictions established in accordance with the land and other legislation of the Russian Federation as of the date of receipt of a notice of completion of construction, except in cases where these restrictions are provided for by a decision to establish or change a zone with special conditions for the use of the territory adopted in relation to the planned for construction, reconstruction of the capital construction object, and such a capital construction object has not been put into operation. paragraph 1 of this article.

We will launch your business.

Our specialists have sufficient experience and professional connections for the speedy registration of the AIA. You don't have to waste precious time and delay the launch of the object.

Leave all the hard work to us.
We are at your service.

The final stage of the construction of the property is commissioning. The key document for obtaining the certificate of commissioning of the facility is statement of conformity (AIA).

Conclusion of conformity (AIA) is “the conclusion of the state construction supervision body (in the event that state construction supervision is provided) on the compliance of the constructed, reconstructed capital construction facility with the requirements of technical regulations and project documentation, including the requirements for energy efficiency and the requirements for equipping the facility capital construction with metering devices for the energy resources used, the conclusion of state environmental control in the cases provided for by part 7 of article 54 of this Code ”(clause 9 of part 3 of article 55 of the Town Planning Code of the Russian Federation of the Russian Federation).

Commissioning of the capital construction facility is carried out by the technical customer in accordance with the previously agreed project documentation. The more detailed the project for the implementation of construction and installation works, the easier it is to formalize the commissioning of capital construction facilities with strict compliance with all requirements.

Each previous stage of work is documented by acts of concealed work, which must be submitted to the building supervision inspector. All these documents must be kept by the builder during the entire warranty period for the construction of the building.

The block diagram of the commissioning of the capital construction facility is shown below:

An AIA may be refused for the following reasons:

  1. During the construction, reconstruction of the capital construction facility, violations were made of the compliance of the work performed with the requirements of technical regulations (norms and rules), other regulatory legal acts and project documentation, and such violations were not eliminated before the date of issuance of a conclusion on compliance.
  2. There is no act of verification after the completion of construction, reconstruction of the capital construction object.

Other grounds for refusal to issue an AIA for the commissioning of capital construction projects normative documents not provided.

Therefore, for obtaining a conclusion on the conformity of the object the following must be ensured:

a) Compliance of the work performed with the requirements of technical regulations (norms and rules), other regulations.

Control over the fulfillment of the requirements listed in paragraph a) is carried out:

  • daily services technical supervision in the structure of the Developer, with filling in the general work log and special logs provided for by building codes. At the same time, in accordance with the requirements in the field of construction, it is necessary to carry out surveys of hidden works with the execution of relevant documents, monitor the compliance of materials used in the production of construction and installation work in terms of nomenclature, quantity and quality, etc.
  • periodically by supervisory authorities. The obligation to organize interaction with state construction supervision bodies also lies with the Developer's services from the moment the building permit is received. If violations are detected during the inspection process, the developer is obliged to take measures to eliminate these violations and draw up the relevant documents.

From an article by the head of Gosstroynadzor S.P. Bullfinch:

“It should be noted that state construction supervision is carried out from the date of receipt of a notice of the commencement of work (part 5 of article 52 of the Civil Code of the Russian Federation) until the date of issuance of a conclusion on the compliance of the constructed, reconstructed, repaired capital construction facility with the requirements of technical regulations (norms and rules), other normative legal acts and project documentation. Therefore, a positive conclusion on compliance by the state construction supervision authority is issued only if construction supervision was carried out regularly throughout the entire construction period. And if, due to the fault of the developer, such supervision was not carried out, then the supervisory authority has the right to refuse to issue an AIA. The obligation of the state construction supervision body does not include issuing a conclusion on compliance if the object was built or part of the object was erected in violation established order construction.

b) Compliance of the work performed with the project documentation.

In the process of construction of almost any object, it becomes necessary to adjust some design decisions, replace individual materials with similar ones. The developer is obliged to coordinate such changes with the design organization exercising architectural supervision, and to document these circumstances accordingly.

c) Obtaining the act of the final inspection

In accordance with paragraph 26 of RD-11-04-2006 “When conducting a final audit, the procedure for conducting an audit provided for in Chapter III of this Procedure must be observed, and the following must be taken into account:
a) a fully constructed, reconstructed, repaired capital construction object is subject to visual inspection (including individual work performed, building structures, sections of engineering and technical support networks and applied Construction Materials(products);
b) all acts (orders, notices) on the elimination of violations (shortcomings) identified during the implementation of state construction supervision and construction control are subject to verification.

Before the final inspection of the object, the following must be carried out:

Individual testing of equipment and functional testing of individual systems, culminating in a trial run of the main and auxiliary equipment;
- test runs;
- an act of acceptance of the capital construction object (in the case of construction on the basis of a contract).

During the construction and installation of buildings and structures, intermediate acceptances of equipment units and structural elements of the structure, as well as hidden works, should be carried out.

Individual and functional tests of equipment and individual systems are carried out with the involvement of the customer according to design schemes after the completion of all construction and installation work.

Defects and imperfections made during construction and installation, as well as equipment defects identified during individual testing, must be eliminated by construction, installation organizations and manufacturers before the start of integrated testing.

Test runs are carried out during the commissioning of a capital construction facility before comprehensive testing. During a trial run, the operability of the equipment must be checked and technological schemes, operation safety.

Comprehensive testing must be carried out by the customer during the final inspection. During complex testing, the joint operation of the main units and all auxiliary equipment under load is checked.
Comprehensive testing of equipment according to schemes not provided for by the project is not allowed.
Comprehensive testing of equipment is considered to be carried out under the condition of normal and continuous operation of the main equipment for 72 hours with a rated load and design parameters of steam, gas, pressure and flow of water, etc.

In thermal networks, complex testing is considered to be carried out under the condition of normal and continuous operation of the equipment under load for 24 hours with a nominal pressure provided for in the start-up complex.

In electrical networks, comprehensive testing is considered to be carried out under the condition of normal and continuous operation under load of the substation equipment for 72 hours, power lines - for 24 hours.

At the time of signing the final inspection report, a complete set of as-built documentation is required, including:

Inspection certificates:

  • breakdown of axes of a capital object under construction;
  • geodetic center base;
  • hidden work, control over which must be carried out in a timely manner, before the implementation of subsequent work;
  • building structures
  • sections of engineering networks

In addition, the as-built documentation includes as-built production documentation with records of compliance with the work performed in fact. Also contains:

  • executive geodetic schemes;
  • documentation (drawings and diagrams) of sections of engineering networks;
  • results of tests and examinations of construction control;
  • acts of testing the applied technical devices;
  • documents on the quality of building materials;
  • some other data on the actual execution of the project;
  • special logs, the order of which is stipulated in RD-11-05-2007: general work log; journal of design organizations exercising architectural supervision; quality control logs (input and operational).

Good afternoon friends! We discussed notifications in previous articles. But here is the result of all, about the end, what is?

Of course, in the end, we all want to receive from the GOS bodies a conclusion on the compliance of the constructed, reconstructed capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility with metering devices used energy resources.

Here is such a long name for this document, but in short, just AIA.

What it is?

According to part 3 of Art. 55 of the Civil Code of the Russian Federation for objects, it is necessary to submit a list of documents, including a conclusion on compliance issued by the bodies of the GOS.

If someone gives you permission to enter in the absence of this document, then he will be held administratively liable under Part 4 of Art. 9.5 of the Code of Administrative Offenses of the Russian Federation. They can also appeal your permission to enter and cancel it.

This document is issued by the GOS bodies based on the results of implementation during construction. reconstruction of the state construction supervision in accordance with the requirements of Art. 54 GK RF. If you did not notify the GSN authorities about the start of construction and the state construction supervision was not carried out at your facility, then you will not be issued a conclusion on compliance. You will have to put the facility into operation in a judicial proceeding, appointing a forensic examination of the work performed, etc.

What does the conclusion look like?

Click on the picture to enlarge

Usually, an act of final inspection and an order on approval of the conclusion are attached to the conclusion. The form of conclusion is given in RD 11-04-2006.

How to get it

To obtain this document, the developer must take the following steps

  • submit to the GOS authorities
  • if necessary file , subject to verification
  • submit on time
  • upon completion of construction, submit to the GOS bodies
  • after receiving the act of the final inspection without comments, apply for the issuance of an opinion ()

Also, the procedure for obtaining this document is described in detail in RD 11-04-2006.

If you have any questions feel free to ask them in the comments. See you soon.

P.p.s. Friends, I also want to recommend you "Generator and additional documentation - Generator-ID" from the site ispolnitelnaya.com. The program is so simple and effective that it will save a lot of time. I advise everyone to take a look!!!

An example of a completed act on the compliance of the constructed object with the requirements of technical regulations and project documentation

Hello, friends! In the last article, we considered the principle of drawing up an act of a completed construction object, and today we will talk about drawing up an act on the compliance of a constructed, reconstructed capital construction object with the requirements of technical regulations (norms and rules).

This document is required for issuing a commissioning permit. It is established in Part 3 of Art. 55 GRK RF.

Usually it is issued in the form of an act. Below is a sample of the completed version. You can also download the handicap of the act from the link an act of compliance with the parameters signed by the developer and the contractor.

Click on the picture to enlarge.

In addition to these two acts, it is still necessary to draw up an act on the compliance of the parameters of the constructed, reconstructed capital construction facility with the design documentation. Also, this document is needed for issuing a commissioning permit.

You may also be interested in:

Denis, if it's not difficult, explain by the asterisk at points 6 and 7?

1) Reading the explanation, I understand that these items are filled out for objects that do not require compliance certificates (project and technical regulations). Moreover, these points (6 and 7) are just in the act of conformity (which is not required).

2) If we fill out the entire act (it is required), then should we skip paragraphs 6 and 7?

3) If the project is not subject to state expertise, is an act of compliance with the project and those regulations required? And if required, then why do points 6 and 7?

Document confirming the conformity of the constructed object

For private houses built?

I figured it out myself, thanks for the site! A lot of useful information!

Greetings, Alexey. I'm glad you figured it out. Thanks for rating the site.

Question on the act on the conformity of the parameters of the constructed object. The object is an apartment building with engineering networks. In paragraph 3. Linear objects - all on-site networks are listed. What indicators fit, for example, power supply networks - the length of the network or the length of the cable? According to the project, the length of the network is 180 m.p., the length of the cables is 180*4=720 m.p. The cadastral engineer prescribes - the actual length of the network is 720 m.p. (it does not specify the length of the cable or the length of the network). I think there will be problems in obtaining permission to enter the building?

reconstructed an apartment in the Moscow Ring Road with the permission of OWN forces (there is no contractor). How then to draw up an act of a completed construction object and an act on the compliance of the reconstructed capital construction object with the requirements of technical regulations? Should I go to BTI, ZhEK or somewhere else?

The largest free information and reference system of online access to the complete collection of technical regulations of the Russian Federation. Huge database of technical standards ( more than 150 thousand documents) and a complete collection of national standards, authentic to the official database of the State Standard. GOSTRF.com is over 1 Terabyte free technical information for all Internet users. All electronic copies of the documents presented here can be distributed without any restrictions. Distribution of information from this site on any other resources is encouraged. Everyone has the right to unlimited access to these documents! Everyone has the right to know the requirements set out in these regulations!

on compliance of the constructed (reconstructed, repaired) capital construction facility with the requirements of technical regulations

"__" ____________ 200_

Customer _____________________________________ represented by ________________________

Acting on the basis ________________,

General contractor ____________________________ represented by ____________________________

Acting on the basis _______________,

with this certificate we confirm that the constructed (reconstructed, repaired) capital construction object __________________________

(select one) (name

object in accordance with the approved project documentation)

meets the requirements of technical regulations.

2. The construction was carried out according to the project ____________________________________

(name of the body that approved the project, date)

conclusion of the state examination of project documentation _________________

date of conclusion, adjustments)

3. Seasonal work (if the deadlines for their implementation are postponed) for landscaping, top coating of access roads to buildings, sidewalks, utility, playgrounds and sports grounds, as well as finishing elements of building facades must be completed and handed over to the owner in the manner prescribed by the norms within the following terms :

The act of compliance of the parameters of the constructed, reconstructed, repaired capital construction facility with the technical conditions on the territory of the Leninsky municipal district of the Moscow region

<19gt; Заполняется для каждого вида инженерных сетей отдельно.

<29gt; Заполняется в случае привлечения к строительству инженерных сетей и сооружений субподрядных организаций либо организаций, выполняющих "прямые" подрядные договоры с заказчиком (застройщиком, инвестором).

<39gt; Пункт заполняется по объектам, которые не подлежат государственному строительному надзору в соответствии с требованиями п. 1 ст. 54 Градостроительного кодекса РФ и в отношении которых не требуется оформление заключения о соответствии построенного, реконструированного, отремонтированного объекта капитального строительства требованиям технических регламентов (норм и правил) и проектной документации. В указанный перечень должны быть включены материалы лабораторных исследований, испытаний и экспертиз, выполняемых органами Госсанэпиднадзора Московской области.

<49gt; Заполняется для объектов бюджетного финансирования.

<59gt; Заполняется, если на объекте осуществлялся авторский надзор за строительством.

Certificate of compliance of the constructed, reconstructed, repaired capital construction facility with the requirements of technical regulations

Annex No. 4 to the Administrative Regulations of the Administration of the Municipal Formation of the Serebryano-Prudsky Municipal District for the Provision of the Municipal Service "Issuance of a Permit for the Commissioning of a Capital Construction Object"

What else to download on the topic "Municipality9raquo;:

  • We will draw up a high-quality legal document
  • We specialize in all areas of law
  • Ask a question and get an answer within 10 minutes

Website-assistant for the preparation of various contracts.

Templates and forms. Everything is ready, from you - insert your data in the editor and print. If you have a template that you would like to post here, please use the feedback.

Document confirming the conformity of the constructed object sample

on the conformity of the parameters of the constructed (reconstructed,

"__" ____________ 200_

Acting on the basis ________________,

Customer ____________________________________ represented by _________________________

Acting on the basis ________________,

General contractor __________________________ represented by ______________________________

Acting on the basis ______________,

2. Construction (reconstruction, overhaul) of the capital construction object _______________________________________________________________

(name of the object in accordance with

approved project documentation)

located at: _________________________________________________

(indicate the full address of the object with the indication of the subject

Russian Federation, administrative region, etc. and building address)

was carried out under a project that has a positive opinion of the Moscow State Expertise dated "__" ____________________ 200_, No. _______________________, adjustment dated "__" ___________________ 200_ No. _________________________

3. Completed construction (reconstruction, overhaul) capital construction object has the following parameters:

1. Permission to put an object into operation is a document that certifies the construction, reconstruction of a capital construction object in full in accordance with the construction permit, the compliance of the constructed, reconstructed capital construction object with the urban planning plan of the land plot or, in the case of construction, reconstruction of a linear object the territory planning project and the territory surveying project, as well as project documentation.

2. In order to put the facility into operation, the developer shall apply to the federal executive body, the executive body of the constituent entity of the Russian Federation, the local self-government body or an authorized organization exercising state management of the use of atomic energy and state management in the implementation of activities related to the development, manufacture, disposal of nuclear weapons and nuclear power installations for military purposes, or the State Corporation for Space Activities "Roscosmos", which issued a construction permit, directly or through a multifunctional center with an application for issuing a permit to put the facility into operation.

3. To make a decision on issuing a permit to put an object into operation, the following documents are required:

1) title documents for the land plot;

2) the town-planning plan of the land plot or, in the case of construction or reconstruction of a linear facility, a territory planning project and a land surveying project;

3) building permit;

4) an act of acceptance of a capital construction object (in the case of construction, reconstruction on the basis of a contract);

5) a document confirming the compliance of the constructed, reconstructed capital construction facility with the requirements of technical regulations and signed by the person carrying out the construction;

6) a document confirming the compliance of the parameters of the constructed, reconstructed capital construction facility with the design documentation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility with metering devices for the energy resources used, and signed by the person carrying out the construction (the person carrying out the construction and the developer or technical the customer in the case of construction, reconstruction on the basis of a contract, as well as the person exercising construction control, in the event of construction control on the basis of a contract), except for cases of construction, reconstruction of individual housing construction objects;

7) documents confirming the compliance of the constructed, reconstructed capital construction facility with the technical specifications and signed by representatives of organizations operating utility networks (if any);

8) a diagram showing the location of the constructed, reconstructed capital construction facility, the location of engineering and technical support networks within the boundaries of the land plot and the planning organization of the land plot and signed by the person carrying out the construction (the person carrying out the construction and the developer or technical customer in the case of construction, reconstruction on the basis of a contract), with the exception of cases of construction, reconstruction of a linear facility;

9) the conclusion of the state construction supervision body (if state construction supervision is provided) on the compliance of the constructed, reconstructed capital construction facility with the requirements of technical regulations and project documentation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility with metering devices for used energy resources , the conclusion of the federal state environmental supervision in the cases provided for by Part 7 of Article 54 of this Code;

10) a document confirming the conclusion of an agreement on compulsory insurance of civil liability of the owner of a hazardous facility for causing harm as a result of an accident at a hazardous facility in accordance with the legislation of the Russian Federation on compulsory insurance of civil liability of the owner of a hazardous facility for causing harm as a result of an accident at a hazardous facility;

11) an act of acceptance of the work performed for the preservation of a cultural heritage object, approved by the relevant body for the protection of cultural heritage objects, defined by Federal Law of June 25, 2002 N 73-ФЗ "On Cultural Heritage Objects (monuments of history and culture) of the peoples of the Russian Federation", during restoration, conservation, repair of this object and its adaptation for modern use;

12) a technical plan for a capital construction facility prepared in accordance with Federal Law No. 221-FZ of July 24, 2007 "On the State Real Estate Cadastre";

3.1. The document and conclusion referred to in clauses 6 and 9 of part 3 of this article must contain information on the standard values ​​of the indicators included in the energy efficiency requirements of the capital construction facility, and on the actual values ​​of such indicators determined in relation to the constructed, reconstructed capital construction facility as a result of the studies, measurements, examinations, tests, as well as other information, on the basis of which the compliance of such an object with the requirements of energy efficiency and the requirements for its equipment with metering devices for the energy resources used is established. During the construction, reconstruction of an apartment building, the conclusion of the state construction supervision body must also contain information on the energy efficiency class of the apartment building, determined in accordance with the legislation on energy saving and on improving energy efficiency.

3.2. Documents (their copies or information contained in them) specified in paragraphs 1, 2, 3 and 9 of part 3 of this article are requested by the authorities specified in part 2 of this article, in state bodies, local governments and subordinate to state bodies or bodies local self-government organizations that have these documents at their disposal, if the developer has not submitted these documents on his own.

3.3. The documents referred to in clauses 1, 4, 5, 6, 7, 8, 12 and 13 of part 3 of this article shall be sent by the applicant independently if the said documents (their copies or information contained in them) are not at the disposal of public authorities, bodies local self-government or organizations subordinate to state bodies or local self-government bodies. If the documents specified in this part are at the disposal of state authorities, local governments or organizations subordinate to state bodies or local governments, such documents are requested by the body specified in part 2 of this article, in the bodies and organizations at the disposal of which the said documents, if the developer has not submitted these documents on his own.

4. The Government of the Russian Federation may establish, in addition to those provided for by part 3 of this article, other documents necessary for obtaining a permit to put an object into operation in order to obtain in full the information necessary for putting a capital construction object on state register.

4.1. To obtain a permit to put an object into operation, it is allowed to require only the documents specified in parts 3 and 4 of this article.

5. The body or authorized organization exercising state management of the use of atomic energy and state management in the implementation of activities related to the development, manufacture, disposal of nuclear weapons and nuclear power plants for military purposes, or the State Space Corporation "Roscosmos", which issued a construction permit , within ten days from the date of receipt of the application for issuing a permit to put the facility into operation, are obliged to ensure the verification of the availability and correctness of the documents specified in Part 3 of this Article, inspection of the capital construction facility and issue the applicant a permit to put the facility into operation or refuse to issue permission, stating the reasons for refusal. During the inspection of the constructed, reconstructed capital construction object, the compliance of such an object with the requirements established in the building permit, urban planning plan of the land plot or, in the case of construction, reconstruction of a linear object, the territory planning project and the territory surveying project, as well as the requirements of project documentation, including including the requirements of energy efficiency and the requirements for equipping a capital construction object with metering devices for the energy resources used, with the exception of cases of construction, reconstruction of an individual housing construction object. If during the construction, reconstruction of a capital construction object, state construction supervision is carried out, inspection of such an object by the body that issued the construction permit is not carried out.

6. The grounds for refusal to issue a permit to put the facility into operation are:

1) the absence of the documents specified in paragraph 3 of this article;

2) non-compliance of the capital construction object with the requirements of the town-planning plan of the land plot or, in the case of construction, reconstruction, overhaul of a linear object, with the requirements of the territory planning project and the territory surveying project;

3) non-compliance of the capital construction object with the requirements established in the building permit;

4) non-compliance of the parameters of the constructed, reconstructed capital construction facility with the design documentation. This basis does not apply to objects of individual housing construction.

6.1. Non-receipt (late receipt) of the documents requested in accordance with parts 3.2 and 3.3 of this article cannot be grounds for refusing to issue a permit to put the facility into operation.

Compliance of the constructed capital construction object

The grounds for refusal to issue a permit to put the object into operation, in addition to the grounds specified in part 6 of this article, is the developer's failure to comply with the requirements provided for in part 18 of article 51 of this Code. In this case, a permit to put the facility into operation is issued only after it is transferred free of charge to the federal executive body, the executive body of the constituent entity of the Russian Federation, the local self-government body or an authorized organization exercising state management of the use of atomic energy and state management in the implementation of activities related to the development , manufacturing, disposal of nuclear weapons and nuclear power plants for military purposes, or the State Corporation for Space Activities Roscosmos, which issued a construction permit, information about the area, height and number of floors of the planned capital construction facility, about engineering and technical support networks, one a copy of a copy of the results of engineering surveys and one copy of each of the sections of the design documentation provided for in paragraphs 2, 8 - 10 and 11.1 of part 12 of Article 48 of this Code, or one copy of a copy of the scheme of the planning organization of the land plot with the designation of the location of the individual housing construction object.

8. Refusal to issue a permit to put an object into operation may be challenged in court.

9. A permit to commission a facility (with the exception of a linear facility) shall be issued to the developer if the federal executive body, the executive body of a constituent entity of the Russian Federation, the local self-government body or an authorized organization exercising state management of the use of atomic energy and state management carrying out activities related to the development, manufacture, disposal of nuclear weapons and nuclear power plants for military purposes, or the State Corporation for Space Activities "Roscosmos", which issued a construction permit, was transferred free of charge a copy of the diagram showing the location of the constructed, reconstructed capital construction facility, the location of networks engineering and technical support within the boundaries of the land plot and the planning organization of the land plot, in order to place such a copy in the information system for ensuring urban planning.

10. Permission to put the object into operation is the basis for state registration of the constructed capital construction object, making changes to the state accounting documents of the reconstructed capital construction object.

10.1. A mandatory annex to the permit to put the object into operation is the technical plan of the capital construction object submitted by the applicant, prepared in accordance with the Federal Law of July 24, 2007 N 221-ФЗ "On the State Cadastre of Real Estate".

11. The permit to put the object into operation must contain information about the capital construction object in the amount necessary for the implementation of its state cadastral registration. The composition of such information must comply with the requirements established in accordance with the Federal Law of July 24, 2007 N 221-FZ "On the State Real Estate Cadastre" for the composition of information in the graphic and text parts of the technical plan.

11.1. After the completion of the construction of a capital construction object, the person carrying out the construction is obliged to transfer to the developer of such an object the results of engineering surveys, design documentation, certificates of examination of works, structures, sections of networks of engineering and technical support of the capital construction object, other documentation necessary for the operation of such an object.

11.2. When carrying out work to preserve a cultural heritage object, a permit for commissioning such an object is issued taking into account the specifics established by the legislation of the Russian Federation on the protection of cultural heritage objects.

(Part 11.2 was introduced by Federal Law No. 315-FZ of October 22, 2014)

12. The form of permission to put an object into operation is established by the federal executive body authorized by the Government of the Russian Federation.

13. Within three days from the date of issuance of a permit to put an object into operation, the body that issued such a permit sends a copy of such a permit to the federal executive body authorized to exercise state construction supervision, if a permit has been issued for the commissioning of capital facilities. construction, specified in paragraph 5.1 of Article 6 of this Code, or to the executive authority of the constituent entity of the Russian Federation authorized to exercise state construction supervision, if a permit has been issued for the commissioning of other capital construction facilities.

document confirming the conformity of the constructed object sample

Appendix N 5 to the Administrative Regulations for the provision of municipal services "Preparation and issuance of permits for the commissioning of capital construction facilities by the administration of the Pavlovo-Posadsky municipal district of the Moscow region"

DOCUMENT ON COMPLIANCE OF THE CONSTRUCTED, RECONSTRUCTED CAPITAL CONSTRUCTION FACILITY WITH THE TECHNICAL CONDITIONS Organizations operating engineering and technical support networks confirm that the facility completed by construction and prepared for commissioning is _____________________________________________ (name of the construction object ________________________________________________________________________________, (reconstruction, overhaul) in accordance with the design documentation) located at: _________________________________________________, (name of the municipal district; settlement or urban district, street, avenue, lane, etc.) complies with the technical conditions for connecting the facility to the engineering and technical support networks ______________________________________________ (indicate the name of the engineering networks connected to the facility _________________________________________________________________ of capital construction) Representatives of organizations operating utility networks: Heat supply _________________________________________________________________________________ (position) (name of organization) (signature) (signature decoding) M.P. Hot water supply _________________________________________________________________________________ (position) (name of organization) (signature) (signature) Cold water supply _________________________________________________________________________________ (position) (name of organization) (signature) (signature) M.P. Wastewater reception (sewage) _________________________________________________________________________________ (position) (name of organization) (signature) (signature transcript) M.P. Power supply _________________________________________________________________________________ (position) (name of organization) (signature) (signature transcript) M.P. Other networks ___________________________________________________________________________ (position) (name of organization) (signature) (signature transcript)

Application №3

ACT

on the compliance of the parameters of the constructed, reconstructed, repaired capital construction facility with the design documentation.

"__" _________ 200g.

1. Representatives of the developer

customer _______________________________

(organization, position, full name) lbuilding contractor (contractor)

(organization, position, full name)

2. Design documentation for construction has been developeddesign organization _______________

(name of design organization)
The construction was carried out according to the project _

(series, project code)

approved ____________________________________________________________________________

(name of the body that approved the project, date)

3. Permission to build an object______________________________________

(number, date of issue)
4. Completed construction, reconstruction, overhaul
capital construction object _____________________________________________________

(Object name)

has the following indicators:


Name of indicator

Unit

By project

actually

1. General indicators of the facility being commissioned

Building volume - Total

including the above ground

total area

Square built-inattached premises

Number of floors

things

2. Non-residential objects

Non-industrial facilities (schools, hospitals,

kindergartens, objects of culture, sports, etc.)

Number of seats Number of visits Capacity

Other indicators

Production facilities

Power Performance Length

(other indicators)foundation materialswall materials floor materials roof materials




Application №3

3. Housing construction objects

Total area of ​​residential premises (for excluding balconies, loggia, veranda terraces)

Number of floors

things

Number of sections

sections

Number of apartments

Total

Including:

1-room

2-room

3-room

4-room

more than 4 rooms

pieces/m²

pieces/m²

pieces/m²

pieces/m²

pieces/m²

pieces/m²

Total area of ​​residentialpremises (taking into accountbalconies, loggias, verandas and terraces)

Foundation materials

Wall materials

Floor materials

Roof materials

4. Construction cost

Construction cost

object - total

including

construction and assembly

works

thousand rubles

thousand rubles

5. Additional information

Based on the information provided

parameters of the capital construction object _____________________________________________

(Object name)

comply with the approved project documentation.

Applications:

Representatives of the developer

Representatives of the customer

"____" ____________ 20__

"____" ____________ 20__

___________________________

___________________________

(signatures, full name)

M.P.

(signatures, full name)

M.P.

representatives of the personbuilding

"____" ____________ 20__

___________________________

(signatures, full name)

M.P.




Application No. 4

ACT

on the compliance of the parameters of the constructed, reconstructed, repaired capital construction facility with the technical conditions for the operation of engineering and technical support networks.

"__" _________ 200g.

(developer, or attracted by the developer or customer on the basis of

___________________________________________________________

(organization, position, full name)


present certificate of completed construction ________________________________________

_______________

(Object name)

2. The construction was carried out by the contractor who completed ___________________

(specify type of work)

and its subcontractors________________________________________________________

(name of company)

performing

(specify types of work)

design organizations____________________________________________________________ _________

_______________________________________________________

(number, date of issue)
___________________________________________

(project series)

approved by ________________________________________________________________

documentation

Title of the document

Date of preparation

Note

according to the acts.

Title of the document

Date of preparation

Note

8. Seasonal work (when the deadlines for their implementation are postponed) according tosidewalks, utility, playgrounds and sports grounds, as well as finishing

Types of jobs

Unit

Scope of work

Deadline

Application No. 4

9. More information ___________________________________________________________

Based on the information provided

Capital construction object __________________________________________

(Object name)

rules).

Applications:

representatives of the personbuilding

(signature, full name) m.p.

* - the item is filled in for capital construction projects that are notthe requirements of paragraph 1 of Article 54 of the Town Planning Code of the Russian Federation, and in relation towhich do not require the issuance of a conclusion on the conformity of the constructed, reconstructed, repaired capital construction object documentation.


Application №2

ACT

on the conformity of the constructed, reconstructed, repairedcapital construction object to the requirements of technical regulations(norms and rules).

"__" _________ 200g.

1. Representative (representatives) of the person carrying out the construction
(developer, or attracted by the developer or customer on the basis of
contract, an individual or legal entity that meets the requirements
legislation of the Russian Federation applicable to persons
constructing) _______________________________________________________

____________________________________________________________________________________________

(organization, position, full name)

Guided by the executive and production documentation, compiled
present certificate of completed construction _________________________________________

____________________________________________________________________________________________

(Object name)

2. The construction was carried out by the contractor who performed_ _________________

__________________________________________________________________________________________ __

(specify the type of work )
and his subcontractors organizations __________________________________________________

(name of company) performing

(specify types of work)

3. Design documentation for construction has been developed
design organizations___________________ ________________ _________________________

(name of design organizations)

4. Building permit__________ _______________________________________________________________

(number, date of issue)

5. The construction was carried out according to the project___________________ _______________

(project series)
approved _______________________________________________________________________

(name of the body that approved the project)

6*. The following production and executive documentation

Title of the document

Date of preparation

Note

7*. The equipment installed at the facility complies with the project andaccepted after individual tests and complex tests according to the acts.

Title of the document

Date of preparation

Note

8. Seasonal work (if the deadlines for their implementation are postponed) according tolandscaping, top coating of access roads to buildings,sidewalks, utility, playgrounds and sports grounds, as well as finishingelements of building facades must be completed and handed over to the investor(to the user) in accordance with the procedure established by the norms within the following terms:

Types of jobs

Unit

Scope of work

Deadline


made in accordance with the requirements of technical regulations (standards rules).

Applications:

representatives of the person,building

* - the item is filled in for capital construction projects that are not are subject to state construction supervision in accordance withthe requirements of paragraph 1 of Article 54 of the Town Planning Code of the Russian Federation, and in relation to which do not require the issuance of a conclusion on the conformity of the constructed, reconstructed, repaired capital construction object requirements of technical regulations (norms and rules) and design documentation.


ACT

acceptance of the capital construction object.

Customer Representative_______________________________________________________________

_________________________________________________________________________________________

(organization, position, full name)

Representative of the person carrying out the construction (contractor) ___________________

________________________________________________________________________________________

Representative of the design organization _______________________________________________

___________________________________________________________________________

(organization position, full name)

Representative of the organization carrying out technical supervision _____________________

___________________________________________________________________________

(organization position, full name)

Representative of the organization exercising architectural supervision ____________________

__________________________________________________________________________________________

(organization position, full name)

Representative of the operating organization ____________________________________

__________________________________________________________________________________________

(organization position, full name)

have drawn up this Act to the effect that_______________________________________________ ____

(name of contractor)

Completed construction, renovation,
overhaul of a capital construction facility______________________

_____________________________________________________________________________________

(name of object, address)

project ________________________________________________________________

(name of design organization, project code)
in accordance with the requirements of the contract contracts ___________________________________

(number, date)

and handed over, and ____________________________________________________________

(name of the customer organization)

accepted the specified object.

Operating organization_______________________________________________ ____


Applications:

Representatives of the developer

Representatives of the customer

"____" ____________ 20__

"____" ____________ 20__

___________________________

___________________________

(signatures, full name)

M.P.

(signatures, full name)

M.P.

representatives of the personbuilding (contractor)

Representative of the design organization

"____" ____________ 20__

"____" ____________ 20__

___________________________

___________________________

(signatures, full name)

M.P.

(signatures, full name)

M.P.

Technical Supervision

"____" ____________ 20__

"____" ____________ 20__

___________________________

___________________________

(signatures, full name)

M.P.

(signatures, full name)

M.P.

Operating organization

"____" ____________ 20__

___________________________

(signatures, full name)

M.P.