Ppr for welding work of pipelines. This page contains samples of documents that are necessary when carrying out work at heights

PROJECT OF WORK PRODUCTION

INSTALLATION OF STEEL STRUCTURES USING THE QUICK-ERECTED TOWER CRANE LIEBHERR 26K.1

1. GENERAL PART

1. GENERAL PART

This work project was developed for the installation of metal structures using a quickly erected tower crane LIEBHERR 26K.1 at the site: "..." at the address: ...

According to SNiP 12-04-2002 "Labor safety in construction. Part 2. Construction production" paragraph 3.3, before the start of construction of the facility, the general contractor must carry out preparatory work on organizing the construction site necessary to ensure construction safety, including:

- clearing the territory;

- installation of construction site fencing;

- installation of a pedestrian protective gallery and walkway;

- installation of stands with fire-fighting equipment, information boards with entrances, entrances, locations of water sources, fire extinguishing equipment;

- laying temporary power supply and lighting networks;

- delivery and placement on the territory or outside of it of inventory sanitary, industrial and administrative buildings and structures;

- re-arrange communications (if necessary);

- cleaning the work site.

The completion of preparatory work must be accepted according to the act on the implementation of occupational safety measures, drawn up in accordance with SNiP 12-03-2001 "Occupational safety in construction. Part 1. General requirements."

Basic standards and guidelines used during development:

- SP 48.13330.2011 "Construction organization" SNiP 01/12/2004;

- SNiP 12-03-2001 “Labor safety in construction”, part 1;

- SNiP 12-04-2002 “Labor safety in construction”, part 2;

- Methodological recommendations on the procedure for developing projects for carrying out work using lifting machines and technological maps for loading and unloading operations. RD 11-06-2007;

- PP-390 “Resolution of the Government of the Russian Federation on the fire safety regime”;

- SP 70.13330.2012 "Load-bearing and enclosing structures". Updated edition of SNiP 3.03.01-87;

- SP 126.13330.2012. "Geodetic work in construction. Updated edition of SNiP 3.01.03-84" ;

- SP 16.13330.2011 "Steel structures". Updated edition of SNiP II-23-81 *;

- PB 10-382-00* “Rules for the design and safe operation of load-lifting cranes”;
________________
* PB 10-382-00 do not apply. Federal norms and rules in the field of industrial safety “Safety rules for hazardous production facilities that use lifting structures” have been approved. - Database manufacturer's note.


- OST 36-28-78 "SSBT. Production processes. Rigging work. General safety requirements";

- OST 36-100.3.04-85 "SSBT. Installation of metal and prefabricated reinforced concrete structures. Safety requirements";

- GOST 24258-88 "Means of scaffolding. General technical conditions";

- GOST 12.1.004-91 "SSBT. Fire safety. General requirements";

- GOST R 12.4.026-2001* "SSBT. Signal colors, safety signs and signal markings";

- GOST 12.4.087-84 "SSBT. Construction. Construction helmets. Technical conditions";

- GOST 12.4.107-82* "Safety ropes. General technical requirements";
________________
* GOST 12.4.107-82 was canceled on the territory of the Russian Federation from 07/01/2013 with the introduction of GOST 12.4.107-2012. - Database manufacturer's note.


- GOST 25573-82 * "Cargo rope slings for construction. Technical conditions";

- GOST R 50849-96 "Construction safety belts. General technical conditions. Test methods."

Only trained and certified personnel are allowed to install structures. Installation teams must have appropriate qualifications.

A log of the assembly of installation connections must be kept at the construction site, indicating the names of the installers, the date of installation of the connections and installation methods.

2. TECHNOLOGY FOR CONSTRUCTION OF STRUCTURES

2.1 Previous work

By the time the construction of the metal frame of the showroom begins, the following work must be completed at the site:

- installation of bored piles;

- cutting out trenches for grillages;

- arrangement of grillages;

- backfilling;

- construction of an inspection hole.

All work must be carried out in accordance with the working design and documented in Certificates.

2.2 Preparatory work

Before starting work on the installation of metal structures, you should:

- clean the grillages from dirt, sediment and concrete deposits;

- incoming quality control of metal structures entering installation;

- use a pencil or marker to mark the marks of the installation, longitudinal axes on the side faces of the structures.

2.3 Installation work

Installation of structures should be carried out using grips in accordance with sheets of graphic part 2-5. It is preferable to install elements “from wheels”. If necessary, use an area in the northern part of the construction site for storing elements (see Stroygenplan).

As the columns and half-timbers are installed, sections of load-bearing reinforced concrete walls (elevator unit) should be erected.

Before installing the load-bearing beams of the coating at elevation. +6.800 (top of column, bottom of beam) within grips 1 and 2, it is necessary to mount the beams of the mezzanine floor at elevation. +3.585 (top of the beam) and erect a section of monolithic flooring.

2.3.1 General sequence of work on installing a metal frame:

1. At the storage site, prepare columns, beams and connections for installation.

2. Install the columns in the design position. Install each column in the following technological sequence:

- Perform slinging of the column.

- Raise the column above ground level by 300 mm, make sure that the slings are securely fastened.

- Perform tilting of the column by lifting and simultaneously turning the boom (or changing the reach) to the stop so that the vertical position of the crane's cargo ropes is maintained.

- Use a LIEBHERR 26K.1 crane (can be replaced with one of similar characteristics) to move the column to the installation site. The column should be delivered to the installation site at a height above 2300 mm away from obstacles encountered along the way.

- When installing a column on a foundation, clean the threads of the anchor bolts from rust and concrete residues with steel brushes, run them with a drill with the appropriate diameter and thread pitch, and check for axial marks.

- Install the column on temporary mounting pads, ensure temporary fastening and alignment of the column on the anchor bolts with paired nuts that fix the position of the base plate.

- Carry out design fastening of the column to the foundation. If necessary, brace the column in two mutually perpendicular directions using struts.

- After installation, unstrap the columns.

3. Install the beams in the design position. Install each beam in the following technological sequence:

- Installers must install a scaffold at the location where the beam is to be installed.

- Sling the beam.

- Use a LIEBHERR 26K.1 crane (can be replaced with one of similar characteristics) to move the beam to the installation site. Bring the beam to the installation site at a height of 500 mm from any obstacles encountered along the way.

- The installer should approach the place where the beam is connected to the column from the scaffold and perform their design fastening. Upon completion of work on securing the beam, the slinger unfastens the elements.

4. Mount the connections in the designed position. Install each connection in the following technological sequence:

- Installers should install a scaffold at the communication installation site.

- Perform slinging connection.

- Use the LIEBHERR 26K.1 crane (can be replaced with one with similar characteristics) to connect the connection to the installation site. The connection should be delivered to the installation site at a height above 500 mm from obstacles encountered along the way.

- The installer from the scaffolding should approach the place where the connection is connected to the beam and column and carry out their design fastening. Upon completion of work on securing the beam, the slinger unfastens the elements.

5. Mount the purlins in the designed position in the following technological sequence:

- Installers should lay temporary flooring from boards 40 mm thick (in two mutually perpendicular layers) along the load-bearing beams.

- Perform slinging of the purlin.

- Using a Liebherr 26 K.1 crane (can be replaced with one of similar characteristics), move the run to the installation site at a height above 500 mm from obstacles encountered along the way.

- The installer should approach the place where the purlin is attached to the beams from the scaffold and carry out the design fastening. Upon completion of work on securing the girder, the slinger unslings the elements.

6. Carry out a visual inspection and draw up a report on the work performed.

Loads must be slinged in accordance with slinging diagrams. For work, slings should be used that correspond to the weight and nature of the load being lifted, taking into account the number of branches and their angle of inclination; slings should be selected so that the angle between their branches does not exceed 90°.

Loads must not be moved while there are people underneath them. The slinger can be near the load while it is being lifted or lowered if the load is at a height of no more than 1000 mm from the platform level.

2.3.2 Crane operation

The work is carried out using a quickly erected tower crane LIEBHERR 26K.1 (can be replaced with one of similar characteristics).

Preparation of the workplace

Before starting work with a crane, you must complete the following:

- install stands with sling diagrams and a table of load weights in the crane operating area and at the storage area;

- install safety signs, sign No. 3 along the border of the dangerous zone, sign No. 2 along the line limiting the crane service area.

Crane operation when installing columns:

The crane operates with a hook lift height limit of 11.05 m, with a maximum reach of 24 m and a danger zone of 8.3 m when installing elements, as well as with a reach of 23 m and a danger zone of 1.7 m during operations on the storage area and when unloading from motor transport.

Crane operation when installing beams and ties:

The crane operates with a hook height limit of 11.4 m, with a maximum reach of 24 m and a danger zone of 3.6 m, as well as with a reach of 23 m and a danger zone of 1.6 m during operations at the storage site and when unloading from vehicles.

Crane operation when installing purlins:

The crane operates with a hook lift height limit of 9.2 m, with a maximum reach of 24 m and a danger zone of 3.5 m, as well as with a reach of 23 m and a danger zone of 1.3 m during operations at the storage site and when unloading from vehicles.

During unloading and installation, loads should be moved parallel to the boundary of the danger zone and prevented from accidentally turning around using flexible guy ropes. The lifting height of the hook should be limited to 6.0 m.

Prohibit the presence of people and the storage of cargo in the danger zone. Measures for the safe operation of cranes should be issued as a supplement to production and job descriptions for personnel operating load-lifting cranes and engineering and technical workers.

Close access to the work area for unauthorized persons not directly related to the work, for which purpose, before starting the crane operation, place a signal fence along the border of the dangerous zone.

Loading and unloading operations

General requirements

At the construction site, reinforcement and formwork elements are unloaded with simultaneous placement on the storage and edging site, individually or in stacks. Dragging loads is prohibited. When storing formwork elements in stacks, lay them in rows in a horizontal position no higher than four rows in height. Spacers with a width of at least 5 cm are laid between horizontal rows.

Before starting work:

- appoint the required number of slingers and signalmen;

Here you can see examples of work projects

PPRk (Crane Work Project)

The installation and safe operation of three tower cranes during the construction of a series of monolithic residential buildings is considered. Due to cramped conditions, the cranes operate with a limited service area.

Stationary tower cranes of the Jaso J110N and Jaso J140N brands erect structures of a 19-story building from elevation 0.000 to elevation. +63.000. The cranes are mounted on foundation supports with a slab elevation of -2.200, with tower anchorage.

The maximum load lifted by cranes at a reach of 2.5-15 m is 5 tons, at a reach of 15-40 m - 2.5 tons.

Tower cranes are used at all stages of construction of the underground and above-ground parts of the building, namely:

  • for unloading from vehicles and storing materials and products as they arrive at the construction site
  • for supplying packs of reinforcement, reinforced mesh and formwork, as well as for supplying concrete in buckets during the construction of monolithic structures
  • for supplying small-piece materials and mortar to the installation horizon
  • for supplying and removing construction equipment, equipment, consumables, etc. from the building.

Project scope: Explanatory note A4 - 35 sheets, drawings A1 - 5 sheets

This is an example of a work permit for the excavation of a pit under the protection of a sheet piling fence. Excavation is carried out in 3 stages.

  • Stage 1. Work at the level of 135.50÷134.60 is carried out by a Hitachi ZX 200 excavator with a bucket capacity of 0.8 m3 (maximum digging radius - 9.75 m, maximum digging depth - 6.49 m) equipped with a backhoe bucket with loading of soil into dump trucks. With a lag of 4 meters from the operation of the Hitachi ZX 200 excavator, the installation of the strapping belt (1 I-beam N45 B2) is carried out. Installation is carried out using a truck crane according to a separately developed design and maintenance plan.
  • Stage 2. Work at level 132.50 is carried out with a Hitachi ZX 200 excavator. At this level, a pit is developed to a design depth of 127.84÷127.84 m, by excavating and moving the soil into a dump truck.
  • With a lag of 4 meters from the operation of the ZX 200 excavator, a spacer structure is made, consisting of a strapping belt (2 I-beams N45 B2), spacers made of pipes 426x10mm in axes 1÷10 and struts, as well as pipes 630x12mm in axes 11÷16. Installation is carried out using a truck crane according to a separately developed design and maintenance plan.

Stage 3. Excavation of slopes is carried out by developing and moving soil with a Bobcat S330 excavator into the work area of ​​a Hitachi ZX 225 grab. The grab brings the developed soil to the surface and loads it into a dump truck. The Bobcat S330 excavator is released from the pit upon completion of the work by a truck crane according to a separately developed PPR.

At the last stage, the berm soil is excavated under the installed jibs of the sheet piling fence of the pit using a mini-excavator.

Project for the installation of a water pipeline using the auger method

Laying a water pipeline in a case constructed using a closed auger tunneling method. The excavation of a rectangular working pit and a round receiving shaft is also being considered.

Work on laying pipes using auger tunneling is carried out in several stages:

  • 1st stage. Pushing the pilot line, consisting of rods and a pilot head, to the length of the interval from the starting pit to the receiving pit. The exact direction of the route is ensured by a system for monitoring the position of the pilot head, information about the position of which is displayed on the monitor screen suspended in the launch shaft.
  • 2nd stage. Punching of casing steel pipes and expander mounted in the starting pit on the last rod of the pilot line within the length of the entire interval between the pits. Pushing out working pipes from the starting pit with simultaneous removal of the squeezed out casing steel pipes in the receiving pit.
  • The casing pipes are being pressed with a drilling head at the head of the pipe string, which serves to develop soil in the face; soil is transported from the face to the bucket in the starting pit by a screw conveyor.

3rd stage. Pushing working pipes with a diameter less than or equal to the diameter of the casing pipes, with simultaneous pushing of the casing pipes and screw conveyor links into the receiving pit and their disassembly. When the diameter of the working pipes is less than the diameter of the casing, the construction gap (space) formed between the working pipeline and the inner surface of the excavation must be filled with cement mortar.

Project scope: Explanatory note A4 - 25 sheets, drawings A1 - 4 sheets

PPR for installation of sheet piling and bored piles

An example of a project plan for the installation of sheet piling fencing for a pit in the security zone of a power transmission line (power line). Making bored piles: drilling a hole with augers, installing the reinforced frame of the pile with a drilling rig, filling the pile with concrete mixture using the bottom-up method.

Drilling of bored piles Ø620 mm is carried out using a Hitachi-based drilling rig

Drilling of each well should begin after an instrumental check of the grades of the planned surface of the earth and the position of the contour axes on the site.

As concrete is fed into the well, the auger sections are lifted and dismantled, and the level of concrete in the well must be at least 1 m higher than the bottom of the auger. The distance between the bottom of the well and the lower end of the auger when concreting begins should not exceed 30 cm.

Project scope: Explanatory note A4 - 20 sheets, drawings A1 - 6 sheets

Project for the installation of scaffolding

Example of a project plan for installing scaffolding on the facade of a building under construction

Rack-mounted attached clamp scaffolding is a spatial frame-tier system mounted from tubular elements: racks, cross members, longitudinal and diagonal braces, which are connected to each other using node connections - clamps.

The scaffolding is fastened to the wall using anchors placed in holes punched in the walls with a diameter of 14 mm.

Scaffolding must be attached to the wall of the building under construction. Fastening is carried out through at least one tier for fastening racks, through two spans for the upper tier and one fastening for every 50 sq.m of projection of the scaffolding surface onto the building facade.

Project scope: Explanatory note A4 - 38 sheets, drawings A1 - 4 sheets

On what basis are you required to have a PPR? List of normative documents.

Size: 2.07 MBChapter: Date: 04/24/2017Downloads: 56

PROJECT OF WORK PRODUCTION

Installation of a free-standing anchor-corner support on the foundation for a 500 kV overhead line,

type U2 (rotation method)

You can download it in doc format

I General part

This work project (PPR) was carried out on the basis of order No. 1154 dated December 28, 2015 “On the assembly and installation of overhead line supports on the territory of the training ground of the personnel training center”

II Project composition

The PPR includes a technological map for the production of work using jib-type truck cranes, jib-type loader cranes, loader cranes and PS-1 hoists.

III Explanatory Note

In order to improve the qualifications of personnel in linear sections, gain practical experience in assembling and installing supports, increase readiness for performing ATS, as well as equipping a training ground, a Work Project for the installation of a metal free-standing anchor-corner support (type U-2) has been drawn up for further implementation of this project.

The weight of the anchor-corner support type U2 is 5.712 kg.

PPR includes the following stages of work:

Preparatory work. Preparation of the installation site (clearing snow);

Fastening the metal post of the anchor-corner support U2 to the foundation with mounting hinges;

Lifting and securing the support.

Completion of work.

No.

Sequence of operations

Job title

Group

according to EB

Qty,

people

Preparatory work. Preparing the installation site (clearing snow)

Assess the installation site where it is necessary to clear snow (relief, swampiness, soil condition, presence of uncleaned forest, large stones, fresh stumps).

At the installation site, determine the direction of the bulldozer's route moves.

Master

Electrician

Conduct targeted briefing to the brigade with registration in the work permit. The briefing must indicate safety measures during the work, the order of operations, the technology for performing the work, indicate the directions of the bulldozer's route moves, and upon completion of the work indicate the parking place of the bulldozer. The brigade is allowed to work.

Master -responsible work manager;

Electrician -performer of the work (permitting);

Complete the work to prepare the installation site and place the bulldozer in its parking area. Clear the foundations of snow manually (with shovels).

Electrician -performer of the work (permitting);

Bulldozer driver- crew member

Complete the work.

Master -responsible work manager;

Electrician -performer of the work (permitting);

Fastening the metal rack of the anchor-corner support U2 to the foundation with mounting hinges

Check the compliance of the dimensions at the centers of the reinforced concrete footings (foundations) with the dimensions of the support, as well as the vertical marks of the foundations.

If deviations exceeding the established tolerances are detected, the support may be lifted only after the detected defects have been eliminated.

Inspect the structure of the support post being installed and make sure that there is no possibility of it falling. The presence of all bolted connections and structural elements of the support. Check tools, devices, protective equipment and materials.

Protect the danger area with tape.

Master -responsible work manager;

Electrician -performer of the work (permitting);

Conduct targeted briefing to the brigade with registration in the work permit. The briefing must indicate safety measures during work, the order of operations, technology for performing work, and the danger zone. The brigade is allowed to work.

Master -responsible work manager;

Electrician -performer of the work (permitting);

Brigade

Install the truck crane at the workplace in accordance with Appendix No. 1.

Truck crane operator- crew member

Master

(responsible

Install the hinges onto the support leg foundations (using wood blocks to align the hinge after installing the support) and onto the support shoes.

Truck crane operator- crew member

Sling the support post. Using a truck crane, bring the support stand and shoes to the foundations. Secure the support shoes to the hinges. At the place where the cable support is attached, install wooden spacers to prevent the support from touching the ground and to level the support horizontally.

Truck crane operator- crew member

Electrician (slinger) - team member

Attach two loop slings to the support post (at a distance of 17 m from the base of the support) and insert a Ø 23 mm mounting rope to the traction mechanism (in accordance with Appendix No. 2). Similarly, from the opposite side of the support, lead the cable to the brake mechanism.

Electrician - team member

Install a sling for lifting the support column with a release device, securing it to the crane hook. Install wooden pads under the sling (or inventory pads under the sling). (in accordance with Appendix No. 2).

Truck crane operator- crew member

Electrician (slinger)- crew member

Lifting and securing the support.

Arrange the vehicles in accordance with Appendix 1. Before starting to lift the support, remove uninvolved personnel from the danger zone (during the process of installing the stand, before moving the mechanisms, it is also necessary to remove uninvolved personnel from the danger zone).

Master -responsible work manager

(responsible for safe performance of work using PS)

Bulldozer driver- team member;

The truck crane smoothly lifts the support. The traction machine smoothly begins to move from the support column, the brake machine moves towards the traction machine so as to prevent the creation of slack. Raise the support post to a height of 200-300 mm.

Master -responsible work manager

Bulldozer driver- team member;

Truck crane operator- crew member

Check the serviceability of traction mechanisms, rigging devices, installation of braces, as well as the correctness and reliability of fastening of all rigging under load.

Master -responsible work manager

(responsible for safe performance of work using PS)

The truck crane smoothly lifts the support. The traction machine smoothly begins to move from the support column, the brake machine moves towards the traction machine so as to prevent the creation of slack. Raise the support post to an angle of 35-40 degrees from ground level. Remove the load from the truck crane and transfer it to the traction mechanism.

Master -responsible work manager(responsible for the safe performance of work using PS)

Bulldozer driver- team member;

Truck crane operator- crew member

Pull out the release device, releasing the hook of the truck crane. Move the truck crane to the transport position and remove it from the danger zone.

Truck crane operator- crew member

Electrician -performer of the work (permitting);

The traction machine smoothly begins to move from the support column, the brake machine moves towards the traction machine so as to prevent the creation of slack. Install the support post on the foundations.

Master -responsible work manager

Bulldozer driver- team member;

Install square washers on the rack shoes and screw nuts onto the anchor bolts. In this case, the nuts should not reach close to the surface of the rack shoes.

Electrician - team member

Use a traction machine to apply tension to the cable to slightly tilt the support post. Remove the hinges. Move the traction machine back smoothly to place the support stand on the foundations.

Master -responsible work manager

Bulldozer driver- team member;

Align the support post according to tolerances. If necessary, to level the support post, install shims between the fifth support and the foundation.

Master -responsible work manager

Electrician -performer of the work (permitting);

Tighten the nuts and locknuts of the anchor bolts. Weld the pads to the heel of the rack. Weld the washers of the anchor bolts on three sides.

Master -responsible work manager

Electrician - team member

Electric and gas welder- crew member

Completion of work.

The electrician climbs onto the support post with the endless rope block to the place where the rigging is attached, stands on the lanyard, securing the safety harness lines to the support structure, and secures the endless rope block to the support post.

Electrician -performer of the work (permitting);

Electrician - team member

For electricians on the ground, lift the installation tool along an endless rope in a cotton bag.

Electrician -performer of the work (permitting);

Electrician - team member

Electricians on the ground should hold the endless rope to prevent sudden lowering of the rigging. Lower the rigging and tools to the ground one by one.

Electrician -performer of the work (permitting);

Electrician - team member

The electrician, located on the support, lowers the endless rope block to the ground.

Electrician -performer of the work (permitting);

Electrician - team member

Remove the workplace, rigging, tools, equipment.

The whole brigade

Remove the team from the workplace

Electrician -performer of the work (permitting);

Complete the work.

Master -responsible work manager

Electrician -performer of the work (permitting);


PROJECT OF WORK PRODUCTION

PROJECT OF WORK FOR INSTALLATION OF TECHNOLOGICAL PIPELINES FOR LINKING TECHNOLOGICAL EQUIPMENT WITH PAINTING AND THERMAL INSULATION DEVICE KUPNK. Title 205

PROJECT OF WORK PRODUCTION
FOR INSTALLATION OF TECHNOLOGICAL PIPELINES LINKING TECHNOLOGICAL EQUIPMENT WITH PAINTING AND THERMAL INSULATION DEVICE KUPNK. Title 205

1 GENERAL DATA

A work project is an organizational and technical document for production purposes, which regulates the rules for conducting construction work and the deadline for their execution, the procedure for engineering equipment and arrangement of the construction site, and labor protection and safety measures. The work project determines the technological discipline at the construction site, the quality, timing and safety of the work.

This work project was developed for the installation of process pipelines piping process equipment with painting and thermal insulation.

The project was developed based on the following sets of drawings:

- 5747203-(367-2/08)-3022-205-TI;

- 5747203-(367-2/08)-3022-205-TI.VIT;

- 5747203-(367-2/08)-3022-205-TI.THM.

The work process is regulated by the following regulatory and guidance documents:

1. SNiP 12-01-2004 "Organization of construction";

2. SNiP 3.01.03-84* “Geodetic work in construction”;
________________
* SNiP 3.01.03-84 are not valid. In exchange, SP 126.13330.2012 applies

3. SNiP 3.02.01-87* "Earth structures, foundations and foundations";
________________
* SNiP 3.02.01-87 are not valid. Instead, SP 45.13330.2012 "Earth structures, foundations and foundations. Updated edition of SNiP 3.02.01-87" was put into effect. - Database manufacturer's note.


4. SNiP 3.03.01-87 "Load-bearing and enclosing structures";

5. SNiP 3.04.03-85 “Protection of building structures and structures from corrosion”;

6. SNiP 3.01.04-87 "Acceptance into operation of completed construction facilities. Basic provisions";

7. SNiP 12-03-2001 “Labor safety in construction” part 1;

8. SNiP 12-04-2002 “Labor safety in construction” part 2;

9. SP 12-135-2003 "Labor safety in construction. Industry standard instructions on labor protection";

10. PPB-01-03* "Fire Safety Rules in the Russian Federation", Ministry of Emergency Situations;
________________
* PPB-01-03 don't work. Instead, the Fire Regulations in the Russian Federation apply. - Database manufacturer's note.

11. GOST 23407-78 “Inventory fencing for construction sites and construction sites”;

12. GOST 21779-82 "System for ensuring the accuracy of geometric parameters in construction. Technological tolerances";

13. GOST 7566-94 "Metal products. Acceptance, marking, packaging, transportation and storage";

14. GOST 24846-81 "Methods for measuring deformations of the foundations of buildings and structures";

15. GOST 2246-70 "Steel welding wire. Technical conditions";

16. GOST 23279-85 "Welded reinforcement mesh for reinforced concrete structures and products. General technical conditions";

17. GOST 5781-82* "Hot-rolled steel for reinforcement of reinforced concrete structures. Technical conditions";
________________
* GOST 23279-85 was canceled in the Russian Federation from 07/01/2013 with the introduction of GOST 23279-2012


18. GOST 5264-80 "Manual arc welding. Welded joints. Basic types, structural elements and dimensions";

19. GOST 9467-75 "Coated metal electrodes for manual arc welding of structural and heat-resistant steels. Types";

20. GOST R 52085-2003 “Formwork”;

21. GOST 21.101-97 "Basic requirements for design and working documentation";

22. GOST 24297-87* "Incoming product inspection";
________________
* GOST 24297-87 was canceled on the territory of the Russian Federation from 01/01/2014 with the introduction of GOST 24297-2013. - Database manufacturer's note.


23. GOST 28013-98 * "Construction mortars. General technical conditions";

24. GOST 7948-80 "Steel plumb lines for construction. Technical conditions";

25. GOST 9416-83 "Construction levels. Technical conditions";

26. GOST 7502-98 * "Metal measuring tapes. Technical conditions";

27. GOST 427-75 * "Metal rulers. Technical conditions";

28. GOST 12.3.002-75 "System of occupational safety standards. Production processes. General safety requirements";

29. GOST 12.1.004-85* "System of occupational safety standards. Fire safety. General requirements";
________________
* GOST 12.1.004-85 is not valid. Instead, GOST 12.1.004-91 applies. - Database manufacturer's note.


30. POT RM-007-98* “Inter-industry rules for labor protection during loading and unloading operations and placement of cargo”;
________________
* POT RM-007-98 are not valid. Instead, by order of the Ministry of Labor of Russia dated September 17, 2014 N 642n, the Rules for labor protection during loading and unloading operations and placement of cargo were approved. - Database manufacturer's note.

31. RD 10-40-93 "Standard instructions for engineering and technical workers to supervise the safe operation of lifting mechanisms."

The work project contains:

General provisions, list of equipment and personnel;

- technological map for installation of column block piping;

- technological map for painting the lining of the column block;

Technological map for insulating the piping of a block of columns;

- safety instructions.

Water supply is from the existing water supply.

Electricity supply for the construction period is provided from a distribution cabinet on the construction site, which is powered from the existing power line.

To ensure fire safety during construction, use an existing fire hydrant.

The work project provides for the use of modern means of mechanization of construction processes, compliance with labor protection and safe work requirements, and implementation of environmental protection measures. All workers involved in construction must be trained and have qualification certificates and must be provided with safety helmets and safety vests.

2 ORGANIZATION OF WORK

2.1 Preparatory period

Before starting work at the construction site, the following activities must be completed:

- The work manager, together with the Customer, must issue an approval certificate for construction and installation works on the territory of the existing enterprise, in accordance with clause 4.6 of SNiP 12-03-2001 “Labor safety in construction. Part 1. General requirements in the form of Appendix B;

- appoint by order persons (from among the engineers) certified in the field of industrial safety and having a certificate corresponding to qualifications, responsible for labor protection, quality and proper performance of construction and installation work, fire safety, responsible for the good condition and safe operation of gas and hydraulic machinery and equipment, etc. .d.;

- develop measures for the safe conduct of construction, installation, commissioning and other types of work at the facilities of launch complexes in the conditions of existing production in the form of Appendix No. 6 of instruction No. P2-01 SP-218 I-001;

- issue a permit for construction and installation work in places where hazardous or harmful factors are present, in accordance with clause 4.11 of SNiP 12-03-2001 “Occupational Safety in Construction. Part 1. General Requirements” in the form of Appendix D;

- all workers and specialists before starting work must undergo training in accordance with the requirements of local regulatory documents on safety, industrial sanitation and fire safety in accordance with clause 4.5 of instructions N P2-01 SP-218 I-001;

- arrange a temporary fencing of the construction site with a height of 2 m, in accordance with GOST 23.407-78;

- install a signal fence around the perimeter of hazardous areas during the operation of construction equipment and mechanisms;

- install an information board, as well as temporary road signs;

- arrange a wash of Neva-2 (or equivalent) wheels in case of equipment leaving for the city;

- disconnect and dismantle utility networks that fall into the building area;

- lay temporary power and water supply networks, arrange electric lighting;

- install administrative buildings;

- install temporary warehouses, sheds;

- deliver to the construction site structures and materials located in storage areas in the required quantities;

- deliver and prepare for operation mechanisms, equipment and installation equipment;

- create a geodetic alignment base;

- equip a specially designated area with primary fire extinguishing means;

- provide workers with the necessary tools, equipment, and protective equipment;

- conduct training and briefing of personnel on safety precautions.

2.2 Transportation and storage

The strapping elements should be delivered to the construction site using the MMC FUSO manipulator.

Preparation of metal structures for transportation must comply with GOST 26653. Metal structures with cross-sectional dimensions up to 50 mm inclusive are tied into bundles, skeins or bundles of skeins, and over 50 mm - bundled into bundles at the request of the consumer. Bent profiles are tied into bundles.

The cross-section of packs of metal structures, depending on the size and shape of the cross-section, should approach a circle, rectangle or hexagon. By agreement between the manufacturer and the consumer, a different cross-section of the packs is allowed.

When packing metal structures of measured length, the ends of the bundle must be aligned on one side, the protruding ends on the other side must not exceed the maximum length deviations established in the regulatory documentation (ND) for specific types of rental products. By agreement between the manufacturer and the consumer, packaging without aligning the ends is allowed.

During loading and unloading operations, transportation and storage, metal structures must be protected from mechanical damage, for which they should be laid in a stable position on wooden supports and secured (during transportation) with the help of inventory fasteners, such as clamps, clamps, turnstiles, cassettes, etc. .P. Deformed structures must be rejected and replaced with new ones. Do not drop structures from vehicles or drag them on any surface. During loading, slings made of soft material should be used.

The weight of a pack of metal structures, as well as unpackaged rolled products, should not exceed:

- for manual loading and unloading - 80 kg (up to 25 kg per worker);

- with mechanized loading and unloading - up to 1.6 tons.

The passage of vehicles with metal structures, as well as unloading, must be under the strict control of the person responsible for the safe movement of cargo.

Mineral wool boards and sheet metal are also delivered to the construction site using the MMC FUSO manipulator. The elements and materials received at the construction site are placed in the operating area of ​​the installation crane. All materials must be stored in a position appropriate for transport, sorted by size. It is necessary to store materials under a canopy in conditions that prevent their damage.

2.3 Workplace organization

Workplaces must be illuminated in accordance with the requirements of GOST 12.1.046-85, table 1:

Table 1

Lighting standards for workplaces

Construction sites and work areas

Lowest illumination, lux

The plane in which illumination is normalized

Level of the surface on which illumination is normalized

1. Loading, installation, lifting, unloading of equipment, building structures, parts and materials by cranes

Horizontal

At the sites for receiving and supplying equipment, parts designs and materials

Vertical

On the crane hooks in all positions from the operator's side

2. Non-mechanized unloading and loading of structures, parts, materials and tilting

Horizontal

At cargo reception and delivery sites

3. Installation of structures

Horizontal

Over the entire height of the assembly

Vertical

4. Integrated assembly of strapping elements (docking, welding)

Horizontal

At ground or work surface level

Vertical

Throughout the entire height of work

5. Approaches to workplaces

Horizontal

On formworks, platforms and approaches

6. Storage room for small technological equipment and installation materials

Horizontal

At floor level

Concentrations of harmful substances in the air of the working area, as well as noise and vibration levels at workplaces should not exceed established sanitary and hygienic standards.

Microclimate parameters must comply with sanitary rules and standards for hygienic requirements for the microclimate of industrial premises.

Machines and units that create noise during operation should be operated in such a way that sound levels in workplaces, areas and on the construction site do not exceed the permissible values ​​​​specified in sanitary standards.

When operating machines, as well as when organizing workplaces, to eliminate the harmful effects on workers of increased noise levels, the following should be used:

- technical means (reducing machine noise at the source of its formation; the use of technological processes in which sound levels at workplaces do not exceed permissible levels, etc.);

- remote control;

- individual protection means;

- organizational measures (choice of a rational mode of work and rest, reducing the time of exposure to noise factors in the work area, treatment, preventive and other measures).

Areas with sound levels above 80 dBA are indicated with danger signs. Working in these areas without wearing personal hearing protection is not permitted. Workers are not allowed to stay in areas with sound levels above 135 dBA.

Production equipment that generates vibration must meet the requirements of sanitary standards.

2.4 Geodetic work

During the work, geodetic control is carried out. Control consists of checking compliance with basic design requirements. Geodetic control should be carried out directly during the execution of work, after completion of work at the site or site, when accepting work from the performers.

Alignment work begins with reference to the reference geodetic base; during the construction process, the work must ensure that it is carried out in situ from the points of the geodetic alignment base with a given accuracy of axes and marks.

A geodetic alignment basis for construction should be created taking into account:

- design and existing placement of buildings (structures) and utility networks at the construction site;

- ensuring the safety and stability of signs fixing the points of the alignment base;

- geological, temperature, dynamic processes and other influences in the construction area that may have an adverse effect on the quality of construction of the alignment base;

- use of the created geodetic alignment base during the operation of the constructed facility, its expansion and reconstruction.

The accuracy of constructing the construction site alignment network should be taken in accordance with the data given in SNiP 3.01.03-84*.
________________
* SNiP 3.01.03-84 is not valid. Instead, SP 126.13330.2012 “Geodetic work in construction. Updated edition of SNiP 3.01.03-84” was put into effect. - Database manufacturer's note.


During the operational period the following is checked:

- safety and immutability of the position of the plan-height base;

- compliance with the setting out of structural elements and alignment axes;

- accuracy of transfer of the main axes of structures;

- correctness of the plan-height position of all structural elements.

During the acceptance control process upon completion of construction, the following is controlled:

- compliance of all geometric parameters of the earthen structure with the requirements of the project and regulatory documents;

- timely and reliable completion of as-built surveys during the construction of column block linings and upon its completion.

The result of this work is as-built geodetic documentation.

Geodetic foundation signs must be supervised during the construction process. Their safety and stability are constantly checked.

All geodetic work during the construction period must be recorded in a work log, which is maintained in parallel with the general work log by the supervisor directly carrying out the construction of this facility.

All executive geodetic documentation is signed by the performing surveyor, chief engineer or person responsible for the work. Acceptance and delivery documentation includes:

- As-built surveys of the mounted piping elements of the column block.

All diagrams indicate the design and actual dimensions or deviations from the design dimensions in height and in plan. The coordinate and elevation system is local. The relative level of 0.000 is taken to be 276.150.

Signed as-built surveys are transferred to the Customer along with acts for hidden work to confirm the scope of work completed.

General management of geodetic control is assigned to the chief engineer.

The results of control observations are recorded in logs.

Table 3

List of equipment and tools for geodetic work

Name of equipment, tools

Note

Total station

Level

Leveling rod

Geodetic pole

StandardIf the payment procedure on the payment system website has not been completed, cash
funds will NOT be debited from your account and we will not receive payment confirmation.
In this case, you can repeat the purchase of the document using the button on the right.

An error has occurred

Payment was not completed due to a technical error, funds from your account
were not written off. Try waiting a few minutes and repeating the payment again.

Newly purchased equipment that requires installation also needs to develop a work plan. This project describes in detail the progress of work, according to which the installation of technological equipment should be carried out.

Requirements for PPR for installation of equipment

The document must be in full compliance with construction standards and regulations. Measures for organizing safety, fire safety, and labor protection must be outlined.

The project for the installation of equipment consists of:

  • An explanatory note containing all the details of the requirements for organizing the installation of equipment.
  • The calculation and descriptive part, containing unified solutions for installation, assembly methods, describes the necessary types of welding work.

In the lists of installation equipment and fixtures, the planned volumes of activities and the requirements for materials (pipelines, metal structures, etc.) are calculated. The most suitable technologies for specific installation operations are also identified. This also includes a calendar with work schedules.

  • A package of drawings and diagrams, including enlarged and technological drawings of the assembly of components and equipment, installation diagrams of lifts, equipment, scaffolding, as well as a diagram for connecting temporary electricity, water, gases and steam. The calculations carried out in the computational and descriptive part determine the required amount of energy resources.

The project for the installation of equipment must be confirmed by all parties who intend to take part in the work.

Why is it necessary to develop a work plan for equipment installation?

To optimize work, reduce its duration and reduce costs, it is advisable to use modern mechanization and technological solutions. For these purposes, any Work Production Project is created.

Installation and construction work must be completed within the agreed time frame. At the same time, it is necessary to ensure fire and environmental safety, labor protection. All this is stipulated in the PPR and is mandatory for execution.

Who should develop the PPR

Development of the Project is the responsibility of the organization installing the equipment:

    In the contract construction method, this is the General Contractor.

  • When combining the functions of the Contractor and the Customer, this is the Developer.
  • To perform specialized or individual types of work, this is a Contractor or Subcontractor.

The chief engineer or the head of the organization performing the installation approves ready-made plans for installation of equipment. Certain types of installation work require the development of separate PPR. They are approved by the contractors and must also be agreed upon with the General Contractor.

If installation work will be carried out on the territory of the enterprise, then the PPR should be agreed upon with the organization operating this territory.

According to the rules, the project for the installation of equipment must be agreed upon, approved and transferred to the construction site two months before the start of the planned installation work.