Consolidated construction cost estimates are compiled. What determines the summary estimate?

The summary estimate is the final stage of the process of developing estimate documentation, which determines the cost of construction, including all costs for the construction or reconstruction of objects. After approval, the estimate is the basis for financing construction work.

The summary estimate consists of twelve columns. These columns reflect: temporary, winter or unexpected limited costs; survey and design work; control of work process and compliance with the project; customer service check. An explanatory note is attached to the estimate submitted for approval.

The summary construction estimate reflects the entire list of costs for customers or investors during the construction of the facility. It is better to calculate the cost of construction and approve it personally for non-industrial and industrial types of development.

The estimate is drawn up in the form MDS-8135.2004. Having an example of a summary estimate, you can quickly make your own calculation. Almost all programs for calculating estimates have the ability to calculate a summary estimate. But it is also possible to calculate the data in Microsoft Office Excel, since the main workflow is carried out with local estimates, and not much time is needed to calculate the summary estimate.

Sample summary estimates can be viewed in the book “Fundamentals of Estimating in Construction” by the writer N.I. Baranovskaya. This book also provides data from regulatory and legislative documents that give the right to take into account many costs in the consolidated construction estimate. Comments and explanations are provided on the use of individual standards and legislative documents. Our website provides examples of summary estimates.

 Summary estimate calculation of the cost of construction determines the estimated limit of funds required to fully complete the construction of all objects provided for by the project. A consolidated estimate of the cost of construction, approved in accordance with the established procedure, serves as the basis for determining the capital investment limit and opening construction financing. Consolidated construction cost estimates are compiled and approved separately for production and non-production construction.

In the consolidated estimate of the cost of a project for the construction of an enterprise, building or its phase, the totals for all object estimates (estimates) without amounts to cover limited costs, as well as estimates for individual types of costs, are included in separate lines. Items of the consolidated construction cost estimate must have a reference to the number of the specified estimate documents. The estimated cost of each object provided for by the project is distributed according to the columns indicating the estimated cost of “construction work”, “equipment, furniture, inventory”, “other costs”, “total estimated cost”. The summary estimate for construction is drawn up at the current price level. In the consolidated estimates of the cost of industrial and housing and civil construction, funds are distributed in the following chapters:

  1. Preparation of the construction site;
  2. Main construction projects;
  3. Energy facilities;
  4. Transport and communication facilities;
  5. Other costs and work;
  6. Contents of the directorate (technical supervision) of the enterprise under construction;
  7. Training of operational personnel;
  8. Design and survey work, designer's supervision;

The distribution of objects, work and costs within the chapters is carried out according to the nomenclature established for the relevant industry for a consolidated estimate of the cost of construction. If there are several types of completed productions or complexes, each of which has several objects, grouping within the chapter can be carried out into sections, the name of which corresponds to the name of the productions (complexes).

For capital repair projects of residential buildings, communal and socio-cultural facilities, it is recommended that funds be distributed to the following chapters as part of one estimate:

  1. Preparation of sites (territories) for major repairs;
  2. Main facilities;
  3. Objects for auxiliary and service purposes;
  4. External networks and structures of water supply, sewerage, heat supply and gas supply;
  5. Improvement and landscaping of the territory;
  6. Temporary buildings and structures;
  7. Other work and costs;
  8. Technical Supervision;
  9. Design and survey work, designer's supervision.

The consolidated estimate is drawn up for the entire construction, regardless of the number of general contracting construction and installation organizations participating in it.

The estimated cost of work and expenses to be carried out by each general contracting organization is drawn up in a separate statement, compiled in relation to the form of the consolidated estimate.

An explanatory note is drawn up for the summary estimate submitted for approval as part of the project, which contains:

  • construction location;
  • a list of catalogs of estimate standards adopted for drawing up construction estimates;
  • name of the general contractor;
  • overhead rates;
  • estimated profit standard;
  • features of determining the estimated cost of construction work for a given construction project;
  • features of determining the estimated cost of equipment and its installation for a given construction site;
  • features of determining funds for a given construction project according to chapters 8-12 of the consolidated estimate;
  • calculation of the distribution of funds in the direction of capital investments (for housing and civil construction);
  • other information on the procedure for determining costs specific to a given construction project, as well as links to relevant decisions of government and other public authorities on issues related to pricing and benefits for specific construction.

In the summary estimate of the cost of construction, the following results are given (in columns 4-8): for each chapter (if there are sections in the chapter - for each section), for the sum of chapters 1-7, 1-8, 1-9, 1-12 , as well as after accruing the amount of reserve funds for unforeseen work and costs: “Total according to the consolidated estimate.”

The summary estimate for capital repairs provides the final data for each chapter, for the sum of chapters 1-5, 1-6, 1-7, 1-9, as well as after accruing the amount of the reserve for unforeseen work and costs: “Total for the consolidated estimate calculation."

Funds included in Chapter 1 “Preparation of the construction site”

Includes funds for work and costs associated with the allocation and development of the built-up area. These works and costs include:

  • allotment of a land plot, issuance of architectural and planning assignments;
  • breakdown of the main axes of buildings and structures;
  • clearing the construction area;
  • relocation of residents of demolished houses;
  • compensation for the cost of demolished (moved) buildings and plantings;
  • drainage of the area, etc.

The cost of work is determined on the basis of project volumes and current prices.

The amount of funds should also take into account the cost of work necessary to place temporary buildings and structures on the prepared territory.

Tools included in chapters 2-7

To Chapter 2 " Main construction projects» includes the estimated cost of buildings, structures and types of work for the main purpose.

To Chapter 3 " Utility and service facilities» includes the estimated cost of auxiliary and service facilities: for housing and economic construction - utility buildings, waste bins, etc.

Chapters 4-7 include objects whose list corresponds to the chapter titles.

To Chapter 8 " Temporary buildings and structures» includes funds for the construction and dismantling of temporary buildings and structures, which include production, storage, auxiliary, residential and public buildings and structures that are specially erected or adapted for the construction period and are necessary for construction and installation work and servicing construction workers.

In chapter 9 (7) " Other work and costs» the consolidated estimate for construction (repairs) includes the main types of other work and costs at the current price level:

  • additional costs in winter;
  • costs of maintaining and restoring roads;
  • costs of transporting workers by road;
  • costs associated with organizing work on a rotational basis;
  • costs associated with the use of military construction units, student teams
    etc.

In Chapter 10 " Contents of the directorate (technical supervision) of an enterprise under construction» includes funds for the maintenance of the apparatus of the customer-cutter (the single customer, the directorate of the enterprise under construction) and technical supervision, in the amounts established by the State Construction Committee.

To Chapter 11 " Training of operational personnel» includes funds for training operational personnel for newly built and reconstructed enterprises, determined by calculations based on:

  • the number and qualification composition of workers whose training is planned to be carried out in training centers, technical schools, etc.
  • terms of study;
  • expenses for theoretical and industrial training of workers;
  • wages (scholarships) of workers studying with accruals to it;
  • the cost of travel for trainees to the place of training (internship) and back, etc.

To Chapter 12 " Design and survey work, designer's supervision» funds are included for:

  • performance of design and survey work (services): separately into design and survey work;
  • carrying out designer's supervision of design organizations during construction;
  • conducting an examination of design and pre-project documentation;
  • pile testing;
  • preparation of tender documentation;
  • Fund reserve for unforeseen work and expenses;

The consolidated estimate of the cost of construction includes a reserve of funds for unforeseen work and costs intended to reimburse the cost of work and expenses, the need for which arises in the process of developing working documentation or during construction as a result of clarifying design decisions or construction conditions for objects provided for in the approved project. The reserve is determined from the total of chapters 1-12 in the amount of no more than 2% for social sector objects and no more than 3% for industrial objects.

Funds provided for the results of the consolidated estimate

Following the summary estimate of construction costs, the following is indicated:

  • refundable amounts;
  • the total balance sheet (residual) value of equipment dismantled or rearranged within the reconstructed or technically re-equipped enterprise based on the results of on-site and local estimates and estimates;
  • amounts of funds for the share participation of enterprises or organizations in the construction of public facilities;
  • final data on the distribution of the total estimated cost of construction by areas of capital investment;
  • amount of value added tax (VAT).

Summary estimates of the cost of construction of enterprises, buildings, structures or their queues are documents. determining the estimated limit of funds required to fully complete the construction of all facilities provided for by the project. A consolidated estimate of the cost of construction, approved in accordance with the established procedure, serves as the basis for determining the capital investment limit and opening construction financing. Consolidated construction cost estimates are compiled and approved separately for production and non-production construction.

A summary estimate of the cost of a project for the construction of an enterprise, building, structure or its phase is drawn up according to the form. It includes in separate lines the totals for all object estimates (estimates) without amounts to cover limited costs, as well as estimates for individual types of costs. Items of the consolidated estimate calculation of the cost of construction of enterprises, buildings, structures must have a link to the source of information (estimate documents). The estimated cost of each object provided for by the project is distributed according to columns indicating the estimated cost of construction work, installation work, equipment, furniture and inventory, other costs and the total estimated cost.

The summary estimate for construction is drawn up at the current price level.

In the consolidated estimates of the cost of industrial and housing and civil construction, funds are distributed across the following chapters.

1. “Preparation of the construction site.”

2. “Main construction projects.”

4. “Energy facilities”.

5. “Transport and communication facilities).

6. “External networks and structures of water supply, sewerage,

heat supply and gas supply."

7. “Improvement and landscaping of the territory.”

8. “Temporary buildings and structures.”

9. “Other work and costs.”

enterprises".

11. “Training of operational personnel.”

The distribution of objects, work and costs within the chapters is carried out according to the nomenclature of the consolidated estimate for the cost of construction established for the relevant sector of the national economy. If there are several types of completed productions or complexes, each of which has several objects, grouping within the chapter can be carried out into sections, the name of which corresponds to the name of the productions (complexes).

For certain sectors of the national economy, industry and types of construction, on the basis of regulatory documents on design approved by ministries and other federal executive authorities, the name and nomenclature of the chapters of the consolidated estimate may be changed.

For capital repair projects of residential buildings, communal and socio-cultural facilities, as part of the consolidated estimate, it is recommended to distribute funds according to the following chapters.

1. “Preparation of sites (territories) for major repairs.”

2. “Main objects.”

Z. “Objects for auxiliary and service purposes.”

4. “External networks and structures (water supply, sewerage, heat supply, gas supply, etc.”).

5. “Improvement and landscaping of the territory.”

6. “Temporary buildings and structures.”

7. “Other work and costs.”

8. "Technical supervision".

The estimated cost of work and expenses to be carried out by each general contracting organization is drawn up in a separate statement, compiled in relation to the form of the consolidated estimate.

An explanatory note is drawn up for the summary estimate submitted for approval as part of the project, which contains:

Location of construction, list of catalogs of estimate standards adopted for drawing up construction estimates;

Name of the general contractor (if known);

Overhead cost standards (for a specific contractor or by type of construction, type of construction and installation work);

Estimated profit standard (for a specific contractor or by type of construction, type of construction and installation work);

Features of determining the estimated cost of construction work for a given construction project;

Features of determining the estimated cost of equipment and installation for a given construction site;

Features of determining funds for a given construction project according to chapters 8-12 of the consolidated estimate of the cost of construction;

Calculation of the distribution of funds in areas of capital investment (for housing and civil construction);

Other information about the procedure for determining the cost, the nature of a given construction project, as well as links to relevant decisions of government and other public authorities on issues related to pricing and benefits for specific construction.

The methodology for filling out the consolidated estimate of the cost of construction is such that it involves summing up in columns 4-8 for each chapter (if there are sections in the chapter - for each

for the sum of chapters 1-7, 1-8, 1-9, 1-12, after accrual of the amount of the reserve for unforeseen work and expenses, as well as after accrual of VAT. Similarly, in the summary estimate for capital repairs, the final data for each chapter is given, for the sum of chapters 1-5, 1-6, 1-7, 1-9. after accrual of the amount of reserve funds for unforeseen work and expenses, after accrual of VAT.

Chapter 1 includes funds for work and costs associated with the allocation and development of the developed territory. These works and costs include:

a) allotment of a land plot, issuance of architectural and planning assignments and identification of red building lines;

b) laying out the main axes of buildings and structures and securing them with points and signs;

c) clearing the construction area from existing buildings, forest plantations, industrial dumps and other obstructive objects, relocating residents from demolished houses, rebuilding utility networks, communications, structures, paths and roads, removing and storing fertile soil, etc. ;

d) compensation for the cost of demolished (moved) buildings and plantings belonging to state, public, cooperative organizations and individuals (owners on private property rights); drainage of the construction site, carrying out other activities on it related to the cessation or change of water use conditions, as well as the protection of the environment and the elimination of unfavorable construction conditions;

e) bringing land plots provided for temporary use for the construction period into a condition suitable for use in agriculture, forestry, fisheries, or for other purposes in accordance with the restoration (reclamation) project of disturbed lands;

f) payment for land when withdrawing (buying out) a land plot for construction, as well as payment of land tax (rent) during the construction period;

g) costs associated with payment for work (services) performed by utility and operating organizations that are fully financed (except for those financed by the budget), with the issuance of initial design data, technical conditions and requirements for connecting the designed facilities to utility networks and public communications, as well as carrying out the necessary approvals of design solutions;

h) compensation for losses caused to land users by the withdrawal or temporary occupation of land plots, restriction of their rights or deterioration in the quality of land (the cost of buildings and structures subject to demolition or relocation; the cost of fruit and berry, protective and other perennial plantings, work in progress (plowing, fertilization , sowing and other work); costs necessary to restore the deteriorated quality of land; losses in the form of lost profits caused by the cessation of receiving annual income by land users from the confiscated lands for the coming period necessary to restore the damaged production;

i) compensation for losses of agricultural production caused by withdrawal or restriction of use, deterioration of the quality of agricultural land;

j) other costs associated with the development of the developed territory and compensation for compensation due under current legislation.

The cost of work included in Chapter 1 is determined on the basis of project volumes and current prices. The provisions for determining the size of individual types of costs taken into account in Chapter 1 of the consolidated construction cost estimates are given in Appendix 7.

The amount of funds should also take into account the cost of work necessary to place temporary buildings and structures on the prepared territory.

Chapter 2 includes the estimated cost of buildings, structures and types of work for primary production purposes, determined on the basis of site estimates and calculations.

Chapter 3 includes the estimated cost of auxiliary and service facilities, which include:

For industrial construction - buildings of repair and technical workshops, factory offices, overpasses, galleries, warehouses, etc.;

For housing and civil construction - utility buildings, entrances, greenhouses in hospital and scientific campuses, garbage dumps, etc., as well as the cost of buildings and structures for cultural and social purposes intended to serve workers (free-standing clinics, canteens, shops, public service facilities , other objects) located within the territory allocated for the construction of enterprises.

In the case when a separate project is being developed with a consolidated estimate of the cost of construction of such facilities as a boiler room, power supply line, heating networks, landscaping, roads and others, which are usually indicated in Chapters 3-7 of the consolidated estimate for a complex project, the estimated cost of these objects should be included in Chapter 2 as main objects.

Chapters 4-7 include objects, the list of which corresponds to the titles of the chapters.

Chapter 8 includes funds for the construction and dismantling of titular temporary buildings and structures, which include production, storage, auxiliary, residential and public buildings and structures that are specially erected or adapted for the construction period and are necessary for carrying out construction and installation work and servicing construction workers.

The amount of funds intended for the construction of title buildings and structures can be determined:

According to calculations based on PIC data in accordance with the required set of title temporary buildings and structures;

According to the standards given in the Collection of estimated cost standards for the construction of temporary buildings and structures, as a percentage of the estimated cost of construction and installation work based on the results of chapters 1-7 of the consolidated estimate.

Simultaneous use of these methods is not allowed.

The amount of funds determined by one of the above methods is included in columns 4, 5 and 8 of the consolidated estimate.

Refunds from the sale of materials and parts obtained from the dismantling of temporary buildings and structures are determined by calculations at the prices of possible sales minus the costs of bringing them into a suitable condition and delivering them to storage areas.

Chapter 9 includes funds for the main types of other work and costs at the current price level.

For specific construction conditions, in agreement with the customer and with appropriate justification in Chapter 9, other types of other costs may be taken into account.

In Chapter 10, columns 7 and 8 include funds for the maintenance of the apparatus of the customer-developer (single customer, directorate of the enterprise under construction) and technical supervision.

Chapter 11 includes (in columns 7 and 8) funds for training operational personnel for newly constructed and reconstructed enterprises, determined by calculations taking into account:

The number and qualification composition of workers whose training is planned to be carried out in training centers, training centers, technical schools, training grounds, directly at enterprises with similar production, etc.;

Duration of training;

Expenses for theoretical and industrial training of workers;

Wages (scholarships) of workers studying with accruals to it;

Cost of travel for trainees to the place of training (internship) and back;

Other expenses associated with the training of these personnel.

Chapter 12, in the order specified in Appendix 7, includes (in columns 7 and 8) funds for:

a) performance of design and survey work (services) - separately into design and survey work;

c) conducting an examination of pre-project and design documentation;

d) testing of piles carried out by a contracting construction and installation organization according to the technical specifications of the construction customer;

e) preparation of tender documentation.

The consolidated estimate of the cost of construction includes a reserve of funds for unforeseen work and costs, intended to reimburse the cost of work and expenses, the need for which arises in the process of developing working documentation or during construction as a result of clarifying design decisions or construction conditions for objects (types of work), provided for in the approved project.

The reserve is determined from the total of chapters 1-12 in the amount of no more than 2% for social facilities and no more than 3% for industrial facilities.

For unique and particularly complex construction projects, the amount of funds for unforeseen work and costs may be increased in each specific case.

The specified funds are shown in a separate line with distribution according to columns 4-8 of the consolidated estimate of the cost of construction.

Part of the reserve of funds for unforeseen work and costs provided for in the consolidated estimate, in the amount agreed upon by the customer and the contractor, may be included in the fixed contract price for construction products. When making payments between the customer and the contractor for the actual volumes of work performed, this part of the reserve is not transferred to the contractor, but remains at the disposal of the customer.

Additional funds for reimbursement of costs that emerged after approval of the project documentation in connection with the introduction of new legislative and regulatory acts should be included in the consolidated estimate calculation as a separate line (in the relevant chapters) with a subsequent change in the final construction cost indicators and approval of the clarifications made by the authority that approved design documentation, and for construction projects financed from the federal budget - in the manner established by the State Construction Committee of Russia.

Following the summary estimate of construction costs, the following is indicated:

1) refundable amounts taking into account the cost of:

Materials and parts obtained from dismantling temporary buildings and structures in the amount of 15% of the estimated cost of temporary buildings and structures (with a depreciable part of the cost) regardless of the construction period;

Materials and parts obtained from dismantling structures, demolishing and moving buildings and structures, in the amount determined by calculation;

Furniture, equipment and inventory purchased for furnishing residential and office premises for foreign personnel supervising installation of equipment;

Materials obtained through associated mining;

2) the total, based on the results of on-site and local estimates and estimates, the balance sheet (residual) value of equipment dismantled or rearranged within the existing reconstructed or technically re-equipped enterprise;

3) amounts of funds for the share participation of enterprises and organizations in the construction of public facilities or general facilities.

4) final data on the distribution of the total estimated cost of construction of a microdistrict or a complex of residential and public buildings by areas of capital investment in the case when this construction includes built-in, attached or free-standing buildings and structures related to various areas of capital investment.

The estimated cost of buildings and works common to all objects included in the microdistrict or complex is distributed:

For intra-apartment (yard) water supply, sewerage, heat and energy supply networks - in proportion to the area of ​​the plots;

For landscaping and landscaping of the territory - in proportion to the area of ​​the plots;

In other cases - in proportion to the total area of ​​buildings (structures);

5) the amount of value added tax is taken from the final data for the consolidated estimate for construction and is shown in a separate line (in columns 4-8). At the same time, in order to avoid double counting, the accrual of VAT on the cost of materials, as well as on transport and other types of services, should not be taken into account in the compiled local and object estimates (estimates).

What is a summary estimate?

The summary estimate determines the cost of construction (CCP), i.e. total costs of the investor and customer for the construction (reconstruction, major repairs) of enterprises, buildings and structures. The approved consolidated estimate serves as the basis for financing construction.

The summary estimate includes 12 columns

They define:

  1. all limited costs (temporary, winter and unforeseen),
  2. design and survey work,
  3. customer service content,
  4. designer's supervision (supervision of designers) over the compliance of the project and the execution of work.

All costs incurred by the investor (customer) during construction must be reflected in the Consolidated Estimate.

Drawing up a summary estimate

A consolidated estimate of the cost of construction is drawn up using the standard form MDS-8135.2004.

The Consolidated Estimate is described in great detail in the book by N.I. Baranovskaya “Fundamentals of estimating in construction”, Moscow 2005.

Almost all automated estimating programs have functions for calculating the Summary Estimate. But you can do the calculation in Excel, because... the main work is carried out with local estimates (work in the Ter and Fer databases for the project), and the summary estimate does not take much time.

Having a ready-made table (fish) for calculations with the entered formulas. I provide an example of a calculation in Excel. If you have any questions, write.

I will try to answer all your questions and be useful to estimators, both experienced and those starting their careers in this exciting profession.

The procedure for drawing up summary estimates

and object estimates in the 2001 database.

Types of estimate documentation.

To determine the estimated cost of construction of buildings and structures in accordance with MDS 81-1.99, p.2.2, the following documentation is drawn up:

The project includes:

Cost summary (if necessary);

Summary estimate of construction costs;

Object and local estimate calculations;

Estimates for individual types of costs.

As part of the working documentation (RD):

Object and local estimates.

Local estimatesare primary estimate documents and are compiled for certain types of work and costs for buildings and structures or general site work based on the volumes determined during the development of working documentation (DD) and working drawings.

Local estimates are drawn up in cases where the scope of work and the amount of costs are not finally determined and are subject to clarification on the basis of the RD, or in cases where the scope of work, the nature and methods of their implementation cannot be sufficiently accurately determined during the design and are clarified during the construction process.

Object estimatesThey combine data from local estimates for the object as a whole and are estimate documents on the basis of which contract prices for objects are formed.

Object estimate calculations combine in their composition the data from local estimates and their calculations for the object as a whole and are subject to clarification, as a rule, on the basis of the RD.

Estimates for individual types of costs are drawn up in cases where it is necessary to determine, as a rule, for the construction as a whole, the amount (limit) of funds necessary to reimburse those costs that are not taken into account by the estimated standards (for example: compensation in connection with the seizure of land for development, expenses associated with application of benefits and additional payments established by government decisions, etc.).

Summary estimate the costs of construction of enterprises, buildings and structures (or their queues) are compiled on the basis of object estimates, object estimates and estimates for individual types of costs.

Simultaneously with the estimate documentation, at the user’s request, the following can be developed as part of the project and DD:

- Statement of the estimated cost of construction of facilities included in the launch complex. It is compiled in the case when the construction and commissioning of an enterprise, building and structure is planned to be carried out by separate start-up complexes. This statement includes the estimated cost of the objects included in the launch complex, as well as general site work and expenses.

The statement of the estimated cost of construction of launch complexes is compiled in the form of a consolidated estimate.

-Statement of the estimated cost of objects and work to protect the natural environment is drawn up in the case when during the construction of an enterprise, building and structure it is planned to take measures to protect the natural environment. The statement includes only the estimated cost of objects and work directly related to environmental protection measures.

Estimate documentation is drawn up in the prescribed manner, regardless of the method of construction - contract or economic method.

Object estimates.

Object estimatesare compiled on the basis of local estimates, in which the cost of work can be determined at one price level: at the base price or at the current price level, according to MDS 81-1.99, form No. 3, Appendix 2.Data from local estimates are grouped according to the estimated cost columns: “construction work”, “installation work”, “equipment, furniture and inventory”, “other costs”.

For determining full cost of the object required for settlements between the customer and the contractor, additional funds are included in the cost of construction and installation work to cover limited costs, namely:

- temporary buildings and structures;

- winter price increases;

- part of the fund reserve for unforeseen work and expenses (agreed upon by the customer and contractor at a fixed free (negotiable) price for construction) .

Temporary buildings and structures are determined according to GESN 81.05.01.2001 “Collection of estimated standards and costs for the construction of temporary buildings and structures.”

These costs are divided into title and non-title (due to overhead costs).

The amount of funds for the construction of title temporary buildings and structures is determined in two ways:

According to % (according to the standard) of the cost of construction and installation work;

According to calculations based on data from the construction organization project (POS).

Simultaneous use of these methods is not allowed.

The procedure for payments for temporary buildings and structures established between the customer and the contractor must be applied from the beginning to the end of construction.

Constructed title temporary buildings and structures are accepted for operation, included in the customer’s fixed assets (except for temporary roads, access roads and architecturally designed fences) and transferred for use to the contractor in the manner established by the contract.

The costs of dismantling temporary buildings and structures are paid upon their liquidation. Materials and structures obtained from the dismantling of temporary buildings and structures are accounted for by the customer's accounting department and sold to the contractor with his consent.

When using prefabricated reinforced concrete slabs for the construction of temporary roads, the return value of the slabs obtained from dismantling is determined on the basis of an act signed by the customer and the contractor.

Winter price increases are included in the object estimate according to the standards established by GESN 81-05-02-2001 “Collection of estimated standards for additional costs when carrying out construction and installation work in winter.”

The collection consists of two sections:

Section I – “Estimate standards for types of construction.”

Section II – “Estimated standards for structures, types of work and temporary heating.”

The norms of Section I are used when drawing up estimate documentation to determine the estimated limit for additional costs associated with carrying out work in winter, as well as settlements between the customer and the contractor.

The norms of Section II are applied when making payments for completed construction and installation work between general contractors and subcontractors, regardless of departmental affiliation.

The rates of additional costs are determined as a percentage of the estimated cost of construction and installation work and are differentiated by temperature zones depending on the temperature conditions of the winter period.

The temperature zone and duration of the estimated winter period for each specific construction site are determined in accordance with the territorial division given in Appendix 1 to the collection GESN 81-05-02-2001, regardless of the actual outside air temperature during the work.

Additional costs for reconstruction and technical re-equipment of existing enterprises are determined according to the standards of Section I from the estimated cost of construction and installation work calculated in accordance with the project.

In areas exposed to wind speeds over 10 m/s, to the standards of the collection in the form of coefficients for the number of wind days in winter:

St. 10% to 30% - 1.05;

St. 30% - 1.08.

The basis for payment of additional costs associated with exposure to wind speeds of more than 10 m/sec in winter is the data of the current Climate Handbook or a certificate from local hydrometeorological service authorities.

Part of the fund reserve for unforeseen work and expenses , provided for in the consolidated estimate, and transferred to the contractor in the amount specified in the contract for inclusion in the composition fixed negotiated price for construction products. When making payments between the customer and the contractor for the actual volumes of work performed, this part of the reserve is not transferred to the contractor, but remains with the customer. In this case, the volumes of actual work performed are recorded in the documents justifying the calculations, including those works that may additionally arise if the customer changes previously adopted design decisions during construction.

In cases where the cost of an object is determined by one local estimate, an object estimate is not drawn up. In this case, the role of the object estimate is played by the local estimate, at the end of which funds are included to cover limited costs in the same order as for object estimates. If the concepts of object and construction coincide, data from local estimates are also included in the consolidated estimate of the cost of construction.

In the object-based estimate (estimate), the unit cost indicators per 1 cubic meter are given line by line and ultimately. m volume, 1 sq. m area of ​​buildings and structures, 1 m length of networks, etc.

Object estimate calculations can be compiled using aggregated estimate standards (indicators), as well as cost indicators for analogous objects.

Summary estimate of construction costs.

Consolidated estimate of construction costs (abbreviated as SSR) - the main document that combines all costs and determines the estimated limit of funds required to fully complete the construction of all objects provided for by the project. Consolidated construction cost estimates are compiled and approved separately for production and non-production construction.

The summary estimate is drawn up at the base, current or forecast price levels. A summary estimate of the cost of a project for the construction of buildings, structures or its phase is drawn up according to Form No. 1 (MDS 81-1.99, Appendix 3).

It includes in separate lines the totals for all object estimates (estimates) without amounts to cover limited costs, as well as estimates for individual types of costs

Items of the consolidated estimate calculation of the cost of construction of enterprises, buildings and structures must have a link to the number of the specified estimate documents. The estimated cost of each object provided for by the project is distributed according to the columns indicating the estimated cost of “construction and installation works”, “equipment, furniture and inventory”, “other work and costs” and “total estimated cost”.

For capital construction projects in summary estimates cost of industrial and housing and civil construction funds are distributed across 12 chapters:

1. “Preparation of the construction site.”

2. “Main construction projects.”

3.

4. “Energy facilities”.

5. “Transport and communication facilities.”

6. “External networks and structures of water supply, sewerage, heat supply and gas supply.”

7.

8.

9. “Other work and costs.”

10. “The content of the directorate (technical supervision) of an enterprise under construction.”

11. “Training of operational personnel.”

12.

The distribution of objects, work and costs within the chapters is carried out according to the nomenclature of the consolidated construction estimate established for the relevant sector of the national economy. If there are several types of completed productions or complexes, each of which has several objects, grouping within the chapter can be carried out into sections, the name of which corresponds to the name of the productions (complexes).

For capital repair projects of residential buildings, municipal and social and cultural facilities as part of summary estimate products recommended distribute over 9 chapters:

1. “Preparation of sites (territories) for major repairs.”

2. “Main objects”.

3. “Objects for auxiliary and service purposes.”

4. “External networks and structures (water supply, sewerage, heat supply, gas supply, etc.).”

5. “Improvement and landscaping of the territory.”

6. “Temporary buildings and structures.”

7. “Other work and costs.”

8. "Technical Supervision".

9. “Design and survey work, designer’s supervision.”

The consolidated estimate is drawn up for the entire construction, regardless of the number of general contracting construction and installation organizations participating in it.

The estimated cost of work and expenses to be carried out by each general contracting organization is drawn up in a separate statement, compiled in relation to the form of the consolidated estimate.

To the summary estimate submitted for approval as part of the project is compiled explanatory note, which provides the following data:

Construction location;

List of catalogs of estimate standards adopted for drawing up construction estimates;

Name of the general contractor (if known);

Overhead cost rates (for a specific contractor or by type of construction) in accordance with MDS 81-4.99;

Estimated profit standard according to MDS 81-25.2001;

Features of determining the estimated cost of construction work for a given construction project;

Features of determining the estimated cost of equipment and its installation for a given construction site;

Features of determining funds for a given construction project according to Chapters 8 - 12 of the consolidated estimate;

Calculation of the distribution of funds in areas of capital investment (for housing and civil construction, if they are determined by the design assignment);

Other information about the procedure for determining costs specific to a given construction project, as well as links to relevant decisions of government and other public authorities on issues related to pricing and benefits for specific construction.

In the summary estimate of construction costs are given (in columns 4-8) the following results: for each chapter (if there are sections in the chapter - for each section), for the sum of chapters 1-7, 1-8, 1-9, 1-12, as well as after accruing the amount of the reserve for unforeseen work and expenses - “Total according to the consolidated estimate.”

In the summary estimate for major repairs are given summary data for each chapter, for the sum of chapters 1-5, 1-6, 1-7, 1-9, as well as after accruing the amount of the reserve for unforeseen work and costs - “Total according to the consolidated estimate”.

Composition of works and costs included in chapters 1,8,9

summary estimate and order their definitions.

Other costsare an integral part of the estimated cost of construction, are included in a separate column of the estimate documentation in the current price level and can relate to both construction as a whole and individual objects and works, teach -

are being in chapters 1 and 9 summary estimate in column 7 in the form of a limit of funds spent by the customer to reimburse the relevant costs.

For a planned construction project, the composition of these works and costs should be clarified based on the specific local conditions of construction.

Tools included in Chapter 1 “Preparation of the construction site”.

1. Registration of a land plot and marking work:

1.1. The allocation of a land plot, the issuance of an APL, the allocation of red building lines are determined by calculation and are included in columns 7 and 8.

Initial data for design, permits, technical conditions and requirements for connecting the designed objects to utility networks and public communications, carrying out the necessary approvals - for calculations and prices for these services (except for the services of budgetary organizations), as well as according to the letter of the Gosstroy of Russia dated November 14 .96 No. BE-19-30/12, (columns 7,8).

1.2. Funds for laying out the main axes of buildings and structures and securing them with points and signs are determined by calculation based on the Collections of prices for survey work and are included in columns 7.8.

Funds for carrying out construction work to secure points and signs in kind are determined by calculation based on the UPSS and are included in columns 4.8.

1.3. Payment for land during the withdrawal (purchase) of a land plot for construction, as well as payment of land tax (rent) during the construction period, is determined on the basis of the Law of the Russian Federation “On Payment for Land” dated October 11, 1991 No. 1738-1 (as amended and additionally ), Land Code of the Russian Federation, Decree of the Government of the Russian Federation dated March 15, 1997 No. 319 “On the procedure for determining the standard price of land” (clause 8, appendix 8), based on the amount of land tax (rates tax) and standard price of land (columns 7,8)

2. Development of the construction area.

2.1. Costs associated with compensation for demolished buildings and gardening plantings, compensation for losses to land owners, landowners, land users, tenants and losses of agricultural production are determined by calculation, based on the “Regulations on the procedure for compensation of losses to land owners, landowners, land users, tenants and losses agricultural production”, approved by the Resolution of the Council of Ministers of the Government of the Russian Federation dated January 28, 1993 No. 77, taking into account amendments dated November 27, 1995 No. 1176 “On amendments to the Resolution dated 01.28.93 No. 77” (columns 7,8).

2.2. Costs associated with the development of the construction site and included in construction and installation work:

Clearing the construction area from existing buildings and structures (demolition or relocation and construction to replace what is being demolished in another place).

Cutting down forests and shrubs, uprooting stumps and removing waste from cutting down trees;

Removal of waste and materials from dismantling that are unsuitable for further use;

Restoration (reclamation) of disturbed lands provided for temporary use during the construction period, i.e. bringing these areas into a condition suitable for use in agriculture, forestry, and fisheries;

Work related to the construction and reconstruction of reclamation systems.

Determined on the basis of design data (scope of work) and current prices for local and site estimates (estimates) (columns 4, 5 and 8).

Places for storage and removal of soil, garbage, materials from the dismantling and felling of plantings that are unsuitable for recycling, as well as quarries for the delivery of missing soil are established by the customer in accordance with the “Regulations on the customer during the construction of facilities for public needs on the territory of the Russian Federation”, approved by the Resolution of the Gosstroy of Russia dated 06/08/01 No. 58, clause 3.1.3.

In cases of reclamation at several geographically separated sites, funds for these purposes may be included in the corresponding site estimates (estimates) for the construction of specific buildings and structures.

2.3. Work related to unfavorable hydrogeological conditions of the construction area and the need to create detours for urban transport.

Determined in accordance with design data, hydrogeological survey data and PIC data according to local and site estimates (budget calculations) (columns 4 - 8).

The amount of funds provided for in Chapter 1 “Preparation of the construction site” of the consolidated estimate should also take into account the cost of work necessary to accommodate temporary buildings and structures.

The procedure for forming the cost of construction for chapters 2 - 7.

Chapter 2 “Main construction projects” includes the estimated cost of buildings and structures and types of work for main production purposes.

In ch. 3 “Objects for auxiliary and service purposes” includes the estimated cost of objects for auxiliary and service purposes:

For industrial construction - buildings of repair and technical workshops, factory offices, overpasses, galleries, warehouses, etc.;

For housing and civil construction - utility buildings, passageways, greenhouses, in hospital and scientific campuses, garbage dumps, etc., as well as the cost of buildings and structures for cultural and community purposes, intended to serve workers, located within the territory allocated for the construction of enterprises.

In the case when a separate project is being developed, with a summary estimate of the cost of construction of such facilities as a boiler room, power supply line, heating networks, landscaping, roads, etc., which are usually indicated in Chapter. 3 - 7 SSR for a comprehensive project, the estimated cost of these objects should be included in Ch. 2 as main objects.

Chapters 4 - 7 include objects, the list of which corresponds to the title of the chapters.

The procedure for determining the amount of funds for temporary

buildings and structures included in Chapter 8.

Chapter 8 of the consolidated estimate includes funds for the construction and dismantling of title temporary buildings and structures necessary for construction and installation work, as well as for servicing construction workers within the construction site or route designated for construction, taking into account adaptation and use for the needs of the construction of existing and newly constructed permanent buildings and structures.

The amount of funds intended for the construction of title buildings and structures may be determined:

According to calculations based on PIC data in accordance with the required set of title temporary buildings and structures;

According to the standards established by the State Construction Committee, as a percentage of the estimated cost of construction and installation work based on the results of Chapters 1-7 of the SSR.

Simultaneous use of these methods is not allowed. The amount of funds determined by one of these methods is taken into account in columns 4, 5 and 8.

The limit of funds for the construction of temporary buildings and structures is determined according to the Collection of estimated cost standards for the construction of temporary buildings and structures (GSN 81-05-01-2001).

The limit of funds for the construction of temporary buildings and structures during repair and construction work is determined according to the Collection of estimated cost standards for the construction of temporary buildings and structures during repair and construction work (GSNr 81-05-01-2001).

The estimate standards specified in GSN 81-05-01-2001 can be used when drawing up estimate documentation for major repairs of industrial buildings, reconstruction and expansion of existing enterprises, buildings and structures, construction of subsequent phases on the territory of existing enterprises or adjacent sites using to the specified norms of the coefficient 0.8.

The procedure for determining the amount of funds included in Chapter 9

“Other work and costs.”

The main costs to be included in Chapter 9 are are:

-Winter price increases.

-Voluntary insurance.

Other work and costs are included in Chapter 9 if necessary and mainly based on PIC data.

Additional costs when carrying out construction and installation work in winter are determined according to the standards of the Collections of estimated standards for additional costs when carrying out construction and installation work in winter (GSN 81-05-02-2001), when carrying out repair and construction work in winter (GSNr 81-05-02-2001). These standards are determined as a percentage of the cost of construction and installation work based on the results of chapters 1-8 for construction projects and 1-6 for major repair projects (columns 4, 5 and 8).

In areas exposed to winds with speeds above 10 m/s, increasing coefficients can be applied to the amount of additional costs calculated according to the standards of the Collections, confirmed by data from the current Russian Climate Handbook and certificates from local hydrometeorological service authorities.

When the number of windy days with a wind speed of more than 10 m/s in winter exceeds 10%:

St. 10% to 30% - 1.05;

over 30% - 1.08.

The above surcharge rates do not apply to capital repairs carried out without stopping the operation of buildings being repaired or in heated buildings, or consisting of eliminating faults in structures, finishing, engineering equipment inside the building while preserving the roof and window fillings.

Costs of maintaining existing permanent roads and restoring them after the completion of highway construction are determined by local estimate calculations based on the PIC in accordance with the design scope of work according to collection No. 27 “Highways” (columns 4, 5 and 8).

Costs of transporting workers of construction and installation organizations by road or compensation of expenses for organizing special routes of urban passenger transport are determined by calculations based on the PIC, taking into account the supporting data of transport enterprises (columns 7 and 8). The costs of transporting workers of construction and installation organizations by motor transport to the place of work and back are allowed to be included in the Consolidated Estimate Calculation in the case where the place of residence (collection point) of workers and employees is located at a distance of more than 3 km from the place of work, and public or suburban transport is either absent or unable to provide transportation for workers.

Costs associated with carrying out work on a rotational basis

Costs associated with the use of military construction units, student detachments and other contingents, as well as with the organized recruitment of workers determined by calculations based on PIC (columns 7 and 8).

Costs associated with sending workers to perform construction, installation and special construction work are determined by calculations based on the PIC or by the estimated labor intensity determined in the estimate documentation (columns 7 and 8), based on the distance to the construction site and the nature of the work performed.

Costs associated with the relocation of construction and installation organizations from one construction site to another determined by calculations based on the PIC (columns 7 and 8).

Costs associated with bonuses for commissioning constructed facilities are determined from the estimated cost of construction and installation work of the consolidated estimate of the cost of construction by calculation according to the letter of the Ministry of Labor of Russia and the State Construction Committee of Russia dated October 10, 1991 No. 1336-VK/1-D and are indicated in columns 7 and 8.

Costs associated with deductions to the research and development fund (R&D) accepted in the amount of 1.5% of the cost of construction products (columns 7 and 8) by agreement with the customer.

Funds to cover the costs of construction organizations on payments (insurance premiums) for voluntary insurance, including construction risks and are accepted in a total amount of up to 3% of the amount of construction and installation work in accordance with Decree of the Government of the Russian Federation dated May 31, 2000 No. 420. At the same time, the total amount of deductions for voluntary insurance of construction risks cannot exceed 2% of the volume of products (works, services) sold. , and the total amount of deductions for insurance of employees against accidents and illnesses, medical insurance and under contracts with non-state pension funds that have a state license is 1% of the volume of products sold (work, services).

Funds to pay expenses associated with leasing construction machines used in construction, installation and repair works are determined according to calculations according to the letter of the State Construction Committee of the Russian Federation dated March 18, 1998 No. VB-20-98/12 (columns 7 and 8). When paying for completed construction and installation work, leasing payments without value added tax are included in the Certificates for completed work based on calculation of actual costs. Funds for leasing payments for technological (domestic and imported) equipment included in the estimates of construction sites, enterprises under construction, reconstruction, buildings and structures are not provided for in the estimate documentation, because These costs are included in the cost of products produced on this equipment after the facility is put into operation.

Funds for organizing and conducting contract bidding (tender) are determined on the basis of calculations by type of cost in accordance with the letter of the Ministry of Construction of Russia dated February 19, 1996 No. VB-29/12-61 (columns 7 and 8).

Costs of supporting government investment programs (providing engineering services) are accepted in the amount of up to 0.15% of the cost of construction and installation work (columns 7, 8), according to the resolution of the State Construction Committee of Russia dated 06/03/93 No. 18-19.

Costs of carrying out special measures to ensure normal working conditions (fighting radioactivity, silicosis, etc.) determined by calculation based on the PIC (columns 7 and 8).

Costs for the maintenance and operation of environmental funds: wastewater treatment plants, ash collectors, wastewater treatment, etc. determined by calculation based on the PIC (columns 7 and 8).

Expenses for fleet rental during the construction of bridges, offshore structures, etc. determined by calculation based on the PIC (columns 7 and 8).

Costs of renting special aircraft for construction and installation work determined by calculation based on the PIC (columns 7 and 8).

Costs of maintaining a mining rescue service are adopted on the basis of standards approved by the State Construction Committee of Russia and relevant agreements.

Costs of monitoring during construction the settlement of buildings and structures erected on subsidence, permafrost, bulk soils, as well as unique objects are determined by calculation based on design decisions and the observation program (columns 7 and 8).

Costs of performing artistic works at construction sites by creative organizations are determined by calculation on the basis of contracts concluded with creative organizations (columns 7 and 8).

Costs of passing storm and flood waters determined by calculations based on the PIC (columns 7 and 8).

Costs of paying fees for transporting oversized cargo on roads and bridges determined by calculations based on the PIC (columns 7 and 8).

Commissioning costs included for social facilities (children's institutions, schools, boarding houses). The amount of funds is determined on the basis of estimates for commissioning work (columns 7 and 8).

In addition, the letter of the State Construction Committee of the Russian Federation dated October 27, 2003 No. NK-6848/10 determined the procedure for allocating costs for commissioning work from November 1, 2003 during the construction of new, expansion, reconstruction and technical re-equipment of existing enterprises, buildings and structures for housing, civil and industrial purposes. Expenses for commissioning work “idle” associated with bringing the facility to a state suitable for use, in accordance with the norms of the article of the Tax Code of the Russian Federation, are taken into account as capital expenses and are included in Chapter 9 of the Consolidated Estimate Calculation (columns 7 and 8). When allocating the costs of commissioning work “idle” to capital investments, one should be guided by the structure of the full complex of commissioning work, taken into account in the new cost estimate and regulatory framework 2001, developed by the State Construction Committee of Russia. The list of works and costs included in Chapter 9 given above can be supplemented for construction, based on specific conditions and features.

Work and costs included in chapters 1, 8 and 9 of the consolidated estimate , can constitute a significant proportion of the total estimated cost of construction and many of them are justified and included in the estimate documentation based on data POS. All this points to the special role of the PIC in the formation of the estimated cost of construction, since it is the PIC that reflects both the working conditions and all other requirements, influencing the estimated cost, both in local and site estimates, and in the SSR.

The procedure for determining the size of means of maintenance

services of the customer-developer under Chapter 10.

The amount of funds for the maintenance of the customer-developer’s apparatus (technical supervision) is determined according to the standards established by the Decree of the State Construction Committee of the Russian Federation dated February 13, 2003 No. 17 (columns 7 and 8) for construction projects financed from the federal budget.

The procedure for determining the amount of funds for preparation

operating personnel for enterprises under construction) under Chapter 11.

Costs are determined by calculation in cases where new technologies are being mastered for which specialists are not trained in the education and training system (columns 7 and 8).

The procedure for determining the amount of funds for project

The cost of design and survey work for construction is determined on the basis of collections and reference books of basic prices developed by the Russian Gosstroy for construction sectors, recalculated to the current level according to indices established by the Russian Gosstroy.

The cost of the examination of pre-project and design documentation is determined in accordance with the “Procedure for determining the cost of work to carry out the examination of pre-project and design documentation for the construction of enterprises, buildings and structures on the territory of the Russian Federation,” approved by Resolution of the State Construction Committee of Russia dated August 18, 1997 No. 18-44.

The cost of development and examination of tender documentation is determined by calculations in agreement with the customer.

The costs listed above are taken into account in columns 7 and 8 of the Consolidated Estimate.

About the reserve of funds for unforeseen work and expenses

The reserve is accrued based on the results of Chapters 1-12 in the amount of no more than 2% for social facilities and no more than 3% for industrial facilities (columns 4-8) and is intended to reimburse the cost of work and expenses, the need for which arises during the design or during construction as a result of clarification of design decisions or construction conditions for objects (types of work) provided for in the approved project.

For unique and particularly complex construction projects, the size of the fund reserve for unforeseen work and costs can be increased in each specific case by agreement with the State Construction Committee. Part of the reserve provided for in the consolidated estimate, in the amount agreed upon by the customer and contractor, may be included in fixed contract prices for construction products.

Additional funds for reimbursement of costs that emerged after the approval of project documentation in connection with the introduction of new legislative and regulatory acts should be included in the consolidated estimate calculation as a separate line (in the relevant chapters) with a subsequent change in the final construction cost indicators and approval of the changes made by the authority that approved design documentation, and for construction projects financed from the federal budget - in the manner established by the State Construction Committee of Russia.

About the funds included at the end of the Consolidated Estimate.

Following the results of chapters 1-12 of the Consolidated estimate and reserve for unforeseen work and costs, the following is shown:

1.Refunds taking into account the cost:

Materials and parts obtained from dismantling temporary buildings and structures, regardless of the period of construction;

materials and parts obtained from dismantling structures, demolishing and moving buildings and structures, in the amount determined by calculation;

Furniture, equipment and inventory purchased for furnishing residential and office premises for foreign personnel carrying out supervision of installation of equipment;

Materials obtained through incidental mining.

The refundable amounts given after the results of the Consolidated Estimate Calculation are summed up from the totals of the refundable amounts shown for reference in the object and local estimates.

2. Total based on the results of object and local estimates and estimates book value (residual) value of equipment, dismantled or rearranged within the existing reconstructed or technically re-equipped enterprise. In this case, the technical and economic indicators of the project are determined taking into account the full cost of construction, which also includes the cost of the rearranged equipment.

3. Amounts of funds for share. The principle for registering the amounts of equity participation as part of the estimate documentation for construction is given in Appendix 3 of SP 81-01-94.

4. Summary data about distribution of the total estimated cost construction of a microdistrict or a complex of residential and public buildings in the areas of capital investment, in the case when this construction includes built-in, attached or free-standing buildings and structures related to various areas of capital investment.

The estimated cost of structures, devices and individual works included in the microdistrict or complex is distributed:

For intra-block (yard) networks of water supply, sewerage, heat and energy supply, etc. - in proportion to the needs of the facility;

For landscaping and landscaping of the territory - in proportion to the area of ​​the plots;

In other cases - in proportion to the total area of ​​buildings (structures).

5. The amount of value added tax (VAT).

The amount of funds for the payment of VAT is accepted in the amount established by the legislation of the Russian Federation from the final data for the Consolidated Estimate Calculation for Construction and is shown in a separate line (columns 4-8) under the name “Funds to cover the costs of paying VAT.” At the same time, in order to avoid double counting, the accrual of VAT on the cost of materials and structures, equipment, as well as on transport and other types of services should not be taken into account in the local and site estimates (estimates) compiled. In cases where the legislation of the Russian Federation establishes benefits for the payment of VAT for certain types of construction projects, this line includes only the funds necessary to reimburse the costs of contract construction and installation organizations in paying VAT to suppliers of material resources and other organizations for the provision of services (including for design and survey work). The amount of these funds is determined by calculation depending on the structure of construction and installation work.

Cost Summary

Cost Summary- this is an estimate document that determines the cost of construction of enterprises, buildings and structures or their queues in cases where, along with industrial facilities, design and estimate documentation is drawn up for housing, civil and other facilities.

The cost summary is compiled according to Form No. 2 (MDS 81-1.99, Appendix 3).

List of used literature:

- “Methodological guidelines for determining the cost of construction products on the territory of the Russian Federation” MDS 81-1.99.

- “Instructions on the procedure for development, coordination, approval and composition of design and estimate documentation” SNiP 11-01-95.

Instructions on the composition, procedure for development, coordination and approval of design and estimate documentation for major repairs” MDS 13.1-99.

- “Collection of estimated cost standards for the construction of temporary buildings and structures” GSN 81-05-01-2001.

- “Collection of estimated cost standards for the construction of temporary buildings and structures during repair and construction work” GSNr 81-05-01-2001.

- “Collection of estimated standards for additional costs during construction and installation work in winter” GSN 81-05-02-2001.

- “Collection of estimated standards for additional costs when carrying out repair and construction work in winter” GSNr 81-05-02-2001.

- “On the amount of funds for bonuses for the commissioning of production facilities and construction projects” letter from the Ministry of Labor of Russia and the State Construction Committee dated October 10, 1991 No. 1336-VK/1-D.

- “On payment of expenses for voluntary insurance of construction risks” Decree of the Government of the Russian Federation dated May 31, 2000 No. 420, letter of the State Construction Committee of the Russian Federation dated March 10, 1998 No. VB-20-82/12.

- “On accounting for leasing payments in estimate documentation” letter from the State Construction Committee of the Russian Federation dated March 18, 1998 No. VB-20-98/12.

- “On the procedure for allocating costs for commissioning work” letter of the State Construction Committee of the Russian Federation dated October 27, 2003 No. NK-6848/10.

- “On the standard costs of maintaining the customer-developer service during the construction of facilities for state needs at the expense of federal budget funds for 2003-2004.” Decree of the State Construction Committee of the Russian Federation dated February 13, 2003 No. 17.

- “The procedure for determining the cost of work to carry out the examination of pre-project and design documentation for the construction of enterprises, buildings and structures on the territory of the Russian Federation” Resolution of the Gosstroy of Russia dated August 18, 1997 No. 18-44

- “Drawing up estimates in construction based on the 2001 estimate and regulatory framework.” A practical guide edited by P.V. Goryachkina.